There are two concurrent projects affecting cable car service. Please also see the California Street Cable Car Infrastructure Improvement Project page. UpdatesThe Cable Car System Improvement Project has been completed. Regular Cable Car Service on the Powell-Mason and Powell-Hyde lines resumed on June 6. Transit alert for Powell-Hyde Cable Car Line, June 1 to 5 The third and final shutdown is scheduled as follows:Effective Wednesday, June 1 to Sunday, June 5 The San Francisco Municipal Transportation Agency (SFMTA) reminds customers, merchants and neighbors that work continues on the two Powell cable car lines and California Cable Car Line. Upon completion of the third and final shutdown as part of the Cable Car System Improvement Project the City’s beloved cable car system will feature new technology and improved quality, reliability, maintenance and safety.
Community Meetings Held on Cable Car System Improvement Project Spring Work, Periodic Shutdowns and Substitute Muni Bus ServiceThe San Francisco Municipal Transportation Agency (SFMTA), which operates Muni, held community meetings about the Cable Car construction this spring on the Powell-Mason, Powell-Hyde and California lines. Construction will entail separate, five-day shutdowns of the Powell-Mason Line and Powell-Hyde Line. As explained in the link above, the California Line was shut down in January and will remain out of service until construction is completed this summer. Aspects of the work discussed at the meeting included construction hours, traffic planning, parking, Muni substitute bus service and other aspects of the project. Community Meetings held: Monday, February 28, 2011 from 6 to 8 p.m. at: and Wednesday, March 9, 2011 from 6 to 8 p.m. at: SFMTA Introduces Spring Cable Car System Improvement Project
|
|||||||||||||||
Shutdown |
Cable Car Line Affected |
Scheduled Dates |
|---|---|---|
Shutdown 1 |
Powell-Mason Line |
3/28-4/1/11 |
Shutdown 2 |
Powell-Hyde Line from Jackson and Powell to the end of the line on Beach and Hyde |
4/25 – 4/29/11 |
Shutdown 3 |
California, Powell-Mason and Powell-Hyde lines |
6/1-6/5/11 |
Please note that the construction schedule may change due to weather or unexpected conditions.
NOTE:
For additional project information and updates please check back on this page. For questions, inquiries or complaints contact us via e-mail at: cablecarupgrade@sfmta.com or call 311 which also provides information in other languages. Kenny Ngan is the Project Manager and can be reached via e-mail at kenny.ngan@sfmta.com
We appreciate your patience while we improve your Muni system.
![]() | Visit the 311 Self-service portal |
![]()
|
For Muni route, schedule, fare and accessible services information anytime: Visit www.sfmta.com or call 311.
Muni transit services are operated by the Transit Division of the San Francisco Municipal Transportation Agency (SFMTA). Copyright © 2000-2012 SFMTA. All rights reserved. Updated February 8, 2012 |
|