Construction

Construction on Phase 1 of the light rail line is complete, except for the Muni Metro East LRV maintenance and storage facility. The SFMTA continues to work with community members and construction contractors to ensure that construction moves forward with minimum impacts. As construction progresses, detailed information will be posted on this web site as well as mailed to residents along the alignment and on our mailing list. Anyone with questions or concerns about construction is invited to contact SFMTA staff.

The construction schedule is as follows (all dates are subject to change):

Location and Description:

Scope of Work

Construction Start

Anticipated Completion

Segment A: 4th Street Bridge (DPW Contract)

  • Seismic retrofit & upgrades
  • Tracks & OCS

April 2003

August 2006

Segment B: Mission Bay (4th/King to Third/22nd)

  • Tracks and Platforms
  • Utilities and Ductbank
  • Light/Strain Poles
  • Traffic and Train Signals
  • Traction Power Cables, Riser Cables, OCS

May 2002

May 2006

Segment C: Central Waterfront (Third/22nd to Third/Jerrold)

  • Tracks and Platforms
  • Utilities and Ductbank
  • Light/Strain Poles
  • Traffic and Train Signals
  • Traction Power Cables, Riser Cables, OCS
  • Seismic retrofit and OCS at Islais Creek Bridge

January 2003

August 2006

Segment D: Bayview/Hunters Point (Third/Jerrold to Third/Donner)

  • Tracks and Platforms
  • Utilities and Ductbank
  • Light/Strain Poles
  • Traffic and Train Signals
  • Traction Power Cables, Riser Cables, OCS
  • Roads, sidewalks and streetscape (Jerrold-Shafter)

December 2002

May 2006

Segment E: Bayview South & US101 Overpass (Third/Donner to Bayshore/Hester)

  • Tracks with retained cut/fill
  • Platforms
  • Utilities and Ductbank
  • Light/Strain Poles
  • Traffic and Train Signals
  • Traction Power Cables, Riser Cables, OCS
  • US 101 Off-ramp with retaining walls
  • Overpass widening

December 2002

June 2005

Segment F: Visitacion Valley (Bayshore/Hester to Bayshore/Sunnydale)

  • Tracks and Platforms
  • Utilities and Ductbank
  • Light/Strain Poles
  • Traffic and Train Signals
  • Traction Power Cables, Riser Cables, OCS

July 2003

July 2004

Segment H: Systemwide Substations and Overhead Contact Systems

  • Substations and Mimic Panel at power central
  • Traction Power SCADA
  • Traction Power Testing

August 2002

May 2006

Segment J: Systemwide Platform Finishes & Systems

  • Canopies, Windscreens, Signage, Furnishings, Art Enhancement and other Platform Finishes
  • Traffic Signal Priority System/VETAG Controllers

March 2003

November 2006

Muni Metro East LRV maintenance and storage facility

  • 13+ Acre Site - Storage for 80 LRVs
  • Foundation work (pile driving)
  • Dewatering work (pumping)
  • Utility work
  • Site work (street and sidewalk improvement, PCC paving for the yard, metal picket fencing, electric gates, irrigation and landscaping, parking lot, site lighting)
  • Track work
  • Overhead Contact System
  • Train Signal System

August 2005

March 2008

 

   
   