L Taraval Improvement Forecast and Project Segment B Update - January 15 - 27, 2024

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit
Walking
Track work between 19th and 22nd Avenue. Pedestrian bridge at 21st Avenue for crossing for evenings and weekends.

L Taraval Improvement Project

Segment B Update – January 15 - 27, 2024

In 2024 we will continue with track work rail installation, and constructing and upgrading boarding islands, curb ramps, and boarding ramps. Underground conduit work is being performed to power the streetlights and OCS poles. Water and sewer line work continues, adding conduits and connections. Streetlights and OCS work continues along this busy corridor. Construction teams will be excavating and jackhammering pavement, which may cause vibrations. Materials are also being temporarily stored nearby. Dust control and housekeeping measures are in place at active construction and staging locations.

Overnight work

Overhead contact system (OCS) pole, overhead wiring and permanent pole placement will be performed along the L Taraval line from Ulloa and Funston to Taraval and Sunset between 10 p.m. and 5 a.m. and is expected to be completed June 2024. Work on any given block will vary and is expected to take a few hours to a few days per location.  

General construction hours are Monday to Friday between 8:00 a.m. and 4:00 p.m. Construction schedules are subject to change. “No Parking” signs will be posted in construction and staging areas, and intersections may be closed to through traffic on Taraval Street

*Please be advised that the construction schedule may be impacted by material availability and coordination between agencies.

Multiple agencies are performing infrastructure work in the area. This includes work by Public Works on 19th Avenue, Public Utilities Commission at Vicente and Wawona streets and PG&E along Taraval Street.

The following L Taraval bus stops will be relocated during construction:

  • The inbound bus stop at Taraval Street and 15th Avenue has been relocated across the intersection until fall 2024.          

January 1 – February 15, 2024

48 Quintera

Inbound

  • 14th and Ulloa to Madrone and Ulloa, northwest corner

Outbound

  • Ulloa and Lenox to West portal and Ulloa, southeast corner
  • 14th and Ulloa to Taraval and 14th, northeast corner
  • 14th and Taraval to northeast corner

January 3 to February 16, 2024

L Taraval / L Special / L Owl

Inbound

  • 15th Avenue to northwest corner 
  • 17th Avenue to Santiago and 17th, southwest corner
  • 19th Avenue to northeast corner
  • 22nd Avenue to Ulloa and 22nd, southwest corner       

Outbound

  • Taraval and Forest Side to Ulloa and Lenox, northwest corner
  • 15th Avenue and Taraval to 17th Avenue and Taraval, southeast corner
  • 19th Avenue to southwest corner
  • 23rd Avenue to southeast corner 

Bus reroute maps are available with temporary bus stop relocations during construction on our website (SFMTA.com/TempStopMap)  

Please note the following impacts to travel during track work: 

  • By car: Taraval Street will be open to through traffic traveling east- and westbound, however, vehicles approaching areas with active track installation will only be able to access Taraval Street by making right turns. At times, traffic may be stopped briefly to allow large machinery to perform work. Please allow extra travel time.
  • By bus: The L Bus may be rerouted around the construction area when heavy equipment is present.
  • On foot: Pedestrians will be able to cross Taraval Street in the construction area at 21st Avenue via a pedestrian access during non-construction hours and weekends.

L Taraval Improvement Project – Segment B

Construction work is scheduled to be performed – January 15 - 27, 2024

Taraval Street

  • 14th Avenue: waterline work, service line connection installation (possible brief disruptions to water service – notices will be distributed)
  • 15th avenue: sawcut and demolish, construct bulb-out, sidewalk and curb ramp
  • 15th - 21st avenues: OCS night work, prep work/ install poles
  • 17th to 18th avenues: accessible platform construction
  • 18th to 19th avenues: construction of accessible platform and boarding island  
  • 21st Avenue: pedestrian bridge
  • 19th to 22nd avenues: track area, demolish and remove rails, construct underground conduit crossings, install rebar mats, construct tracks
  • 24th Avenue: construct catch basin, curb and gutter, grade bulb-out, underground conduits
  • 29th to 30th avenues: boarding island
  • 30th to 31st avenues: boarding island, complete construction
  • 31st to 32nd avenue:  sawcut, demolish and grade curb and sidewalk
  • 33rd to 34th avenues: sawcut, demolish and grade curb and sidewalk
  • 36th Avenue: intersection, water line work, excavate and backfill

Ulloa

  • Forest Side to 15th Avenue: track work, remove, pour and form pavement and foundation

Wawona Street

  • 21st to 23rd avenues: assembled rail stored until installation

Night work

  • On Taraval Street between 19th to 35th avenues: OCS prep work for installation, removing and reconstructing existing poles

Temporary staging locations

  • Ulloa Street south side from 15th to 16th avenues
  • 14th Avenue west side from Ulloa to Taraval streets
  • 22nd Avenue west side from Taraval to Santiago streets

Supporting businesses on Taraval

We continue to support small businesses in the area with current and planned marketing campaigns to support the merchants during construction to drive business to the community:

  • The Mayor’s Office of Economic and Workforce Development (OEWD), in partnership with Shop Dine SF, is creating a landing page on the Shop Dine SF website to highlight small businesses on Taraval.

Please to sign up for email and SMS project updates on the project page.