Van Ness Improvement Project Construction Forecast: January 2-12, 2018

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit sfmta.com/vanness.

Tentative Schedule:

Monday, January 1: In observance of the holiday, no work is scheduled. Happy New Year!

Tuesday, January 2, through Thursday, January 4: Crews will be working on the joint trench to power overhead wires for buses from Golden Gate to Turk. Potholing to assess sub-sidewalk basements (see item below) will occur from Hayes to Sacramento.

Between the hours of 8:00 p.m. and 7:00 a.m. crews will work to update the overhead cables from McAllister to Bush. Crews will work on updating the emergency firefighting water systems from O'Farrell to Sutter. Additionally, crews will pothole for future utility construction from McAllister to Bush streets.

Friday, January 5: Crews will be working on the joint trench to power overhead wires for buses from Golden Gate to Turk. Potholing to assess sub-sidewalk basements (see item below) will occur from Hayes to Sacramento.

Sunday, January 7: Between the hours of 8:00 p.m. and 7:00 a.m. crews will work to update the overhead cables from McAllister to Bush.Crews will work on updating the emergency firefighting water systems from O'Farrell to Sutter. Additionally, crews will pothole for future utility construction from McAllister to Bush streets.

Monday, January 8, through Thursday, January 11: Crews will be working on the joint trench to power overhead wires for buses from McAllister to Turk. Potholing to assess sub-sidewalk basements (see item below) will occur from Hayes to Sacramento.

Between the hours of 8:00 p.m. and 7:00 a.m. crews will work to update the overhead cables from McAllister to Bush. Crews will work on updating the emergency firefighting water systems from O'Farrell to Sutter. Additionally, crews will pothole for future utility construction from McAllister to Bush streets and Jackson to Chestnut.

Friday, January 12: Crews will be working on the joint trench to power overhead wires for buses from McAllister to Turk. Potholing to assess sub-sidewalk basements (see item below) will occur from Hayes to Sacramento.

Basement Assessments

Before utility, roadway and sidewalk work begins, the Van Ness Improvement Project team is inspecting Van Ness Avenue basements that may extend below sidewalks. If your building has a sub-sidewalk basement, or if your building has a basement and you are not sure if it is a sub-sidewalk basement, please email vannessbrt@sfmta.com or 415.646.2317 to schedule a visit.