Van Ness Construction Forecast: July 10, 2017 - July 21, 2017

Monday, July 10: Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission streets. Sawcutting for archeological potholes will take place on Van Ness from Mission to Market streets and Vallejo to Lombard streets.

Tuesday, July 11: Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission streets. Sawcutting for archeological potholes will take place on Van Ness from Mission to Market streets and Vallejo to Lombard streets.

Between the hours of 8:00 p.m. Tuesday and 6:00 a.m. Wednesday, crews will remark traffic lanes traveling northbound from Golden Gate to Turk streets.

Wednesday, July 12 and Thursday, July 13: Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission streets. Potholing for archeological purposes will occur from Greenwich to Lombard streets.

Friday, July 14 and Monday, July 17: Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission streets. Potholing for archeological purposes will occur from Filbert to Greenwich streets.

Tuesday, July 18 and Wednesday, July 19: Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission Streets. Potholing for archeological purposes will occur from Union to Filbert streets.

Thursday, July 20 and Friday, July 21: Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission streets. Potholing for archeological purposes will occur from Green to Union streets.