Van Ness Avenue Construction Forecast: October 16 - October 27, 2017

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit sfmta.com/vanness.

Work is planned over the next months to create two construction zones: one southbound on Van Ness Avenue from Sutter to McAllister streets, and another northbound from Jackson to Lombard streets. These work areas will be approximately five feet from the building line to approximately the center of the roadway.

Those who travel in and through the area are advised to take alternate routes and plan for delays.

Monday, October 16, through Friday, October 20: Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission streets.

Monday, October 23, through Thursday, October 26: Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission streets.

Between the hours of 8:00 p.m. and 7:00 a.m. existing lane striping will be removed and new lanes will be marked between Grove and Pine streets. Neighbors are advised to anticipate construction-related noise, including grinding, as crews work diligently to complete this necessary night work.

Friday, October 27: Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission streets.

Between the hours of 8:00 p.m. and 7:00 a.m. existing lane striping will be removed and new lanes will be marked between Golden Gate Avenue and Bush streets. Neighbors are advised to anticipate construction-related noise, including grinding, as crews work diligently to complete this necessary night work.