FINAL UPDATE: Delay at Powell Station has cleared. IB/OB #subwaysvc resuming normal operations. (More: 31 in last 48 hours)

This page has older content

Please see Related Projects on this page for current project information. We are keeping this page as a record of SFMTA outreach.

Van Ness Avenue Construction Forecast: March 19 - March 30, 2018

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit sfmta.com/vanness.

The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.

Tentative Schedule:
 

Lombard to Greenwich: Night work is scheduled Monday, March 19, through Friday, March 23, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pot hole to confirm underground utilities for upcoming sewer work. Sewer installation is scheduled to occur at the intersection of Greenwich on Monday, March 19 and Tuesday, March 20, between the hours of 8:00 p.m. and 7:00 a.m. Due to sewer installation work, intense noise and vibration is expected during this time.

Filbert to Union: Monday, March 19, through Friday, March 23, crews are scheduled to work on sewer installation at the intersection of Filbert. Intensive noise and vibration is expected.

Night work is scheduled Monday, March 26, through Friday, March 30, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer installation. Intensive noise and vibration is expected.

Union to Green:  Monday, March 26, through Friday, March 30, crews are scheduled to pot hole for upcoming work.

Night work is scheduled Monday, March 26, through Friday, March 30, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer installation at the intersection of Union. Intensive noise and vibration is expected.

Green to Vallejo: Monday, March 19, through Thursday, March 22, crews are scheduled to work on sewer installation and are scheduled to pot hole for upcoming work. Intensive noise and vibration is expected. Friday, March 23, crews are scheduled to pot hole for upcoming work. Monday, March 26, through Friday, March 30, crews are scheduled to work on water main installation.

Broadway to Pacific: Monday, March 19, crews are scheduled to pot hole for upcoming work. Friday, March 23, and Monday, March 26, through Wednesday, March 28, crews are scheduled to work on sewer installation. Intensive noise and vibration is expected. 

Night work is scheduled Monday, March 19, through Wednesday, March 21, and on Monday, March 26, between the hours of 8:00 p.m. and 7:00 a.m., when crews are expected to work on the emergency firefighting water system.

Jackson: Monday, March 19, crews are scheduled to pot hole for upcoming work. 

Night work is scheduled on Monday, March 19, between the hours of 8:00 p.m. and 7:00 a.m., as crews are scheduled to pot hole to confirm underground utilities for upcoming sewer work. Night work is also scheduled Wednesday, March 21, through Friday, March 23, and on Monday, March 26, between the hours of 8:00 p.m. and 7:00 a.m., when crews are expected to work on the emergency firefighting water system.

Clay: Night work is scheduled on Tuesday, March 27, through Friday, March 30, between the hours of 8:00 p.m. and 7:00 a.m., as crews are planning to work on the emergency firefighting water system.

Post: Night work is scheduled on Monday, March 19, and Tuesday, March 20, between the hours of 8:00 p.m. and 7:00 a.m., as crews are scheduled to pot hole to confirm underground utilities for upcoming sewer work. 

Geary to O'Farrell: Thursday, March 22, through Friday March 23 and Monday, March 26, through Friday, March 30, crews are scheduled to work on sewer installation. Intensive noise and vibration is expected.

Night work is scheduled Thursday, March 22, through Friday March 23 and Monday, March 26, through Thursday, March 29, when crews are scheduled to work on sewer installation. Intensive noise and vibration is expected.

O’Farrell to Ellis:  Monday, March 26, through Friday, March 30, crews are scheduled to work on water main installation.

Ellis to Eddy:  Thursday, March 22, through Friday, March 23, and Monday, March 26, through Wednesday, March 28, crews are scheduled to work on sewer installation. Intensive noise and vibration is expected. 

Night work is scheduled Monday, March 19, through Wednesday, March 21, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer installation. Intensive noise and vibration is expected.

Turk: Monday, March 19, through Friday, March 23, and Monday, March 26, through Friday, March 30, crews are scheduled to work on sewer installation. Intensive noise and vibration is expected. Monday, March 26, through Friday, March 30, crews are scheduled to work on a joint utility trench.

Golden Gate to McAllister: Monday, March 19, through Friday, March 23, crews are scheduled to work on a joint utility trench. Monday, March 26, through Friday, March 30, crews are scheduled to pothole for upcoming work.

Night work is scheduled Wednesday, March 21, through Friday, March 23, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on water main installation at the intersection of McAllister.

McAllister to Grove: Night work is scheduled Monday, March 19, through Friday, March 23, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on water main installation.

Grove to Hayes: Wednesday, March 28, through Friday, March 30, crews are scheduled to work on a joint utility trench.

Fell to Hayes: Monday, March 19, through Friday March 23 and Monday, March 26, through Tuesday, March 27 crews are scheduled to work on a joint utility trench.

Fell to Market: Night work is scheduled Monday, March 19, through Friday, March 23, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to install water main at Market Street. Night work is also scheduled Monday, March 26, through Friday, March 30, between the hours of 8:00 p.m. and 7:00 a.m.,  when crews are scheduled to install water main at Oak Street.