FINAL UPDATE: Delay at St. Francis Circle is clearing. Incident #KIngleside train was removed from service. OB #MOceanView and K lines resuming service. (More: 7 in last 48 hours)

This page has older content

Please see Related Projects on this page for current project information. We are keeping this page as a record of SFMTA outreach.

Van Ness Construction Forecast: April 9 - April 20, 2018

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit sfmta.com/vanness.

The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.

Tentative Schedule:

Greenwich: Monday, April 9, through Friday, April 13, and Monday, April 16, through Thursday, April 19, crews are scheduled to work on sewer main installation.

Union: Night work is scheduled Monday, April 16, through Friday, April 20, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Vallejo to Broadway: Tuesday April 17, through Friday, April 20, crews are scheduled to work on sewer main installation.

Broadway to Pacific: Monday, April 9, through Friday, April 13, and Monday, April 16, crews are scheduled to work on sewer main installation.

California to Pine: Night work is scheduled Monday, April 9, and Tuesday, April 10, between the hours of 8:00 p.m. and 7:00 a.m., when crews are expected to work on the emergency firefighting water system.

Pine to Bush: Night work is scheduled Wednesday, April 11, through Friday, April 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are expected to work on the emergency firefighting water system.

Bush to Sutter: Night work is scheduled Friday, April 13, and Monday, April 16, through Friday, April 20, between the hours of 8:00 p.m. and 7:00 a.m., when crews are expected to work on the emergency firefighting water system.

Sutter to Post: Monday, April 9, through Friday, April 13, and Monday, April 16, through Friday, April 20, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Crews are also scheduled to pothole to confirm underground utilities for upcoming sewer work on Monday, April 9, and Tuesday, April 10.

Night work is scheduled Wednesday, April 18, through Friday, April 20, between the hours of 8:00 p.m. and 7:00 a.m., when crews are expected to work on the emergency firefighting water system.

Post to Geary: Monday, April 9, through Friday, April 13, crews are scheduled to install a joint-utility trench.

O'Farrell to Ellis: Monday, April 9, through Friday, April 13, and Monday, April 16, through Friday, April 20, crews are scheduled to work on sewer main installation at the intersection of Ellis. Intensive noise and vibration is expected. Monday, April 16, through Friday, April 20, crews are scheduled to work on water main installation. Crews are also scheduled to pothole for upcoming work on Thursday, April 19, and Friday, April 20.

Eddy to Turk: Monday, April 9, through Friday, April 13, crews are scheduled to work on water main installation at the intersection of Eddy. Wednesday, April 11, through Friday, April 13, and Monday, April 16, through Wednesday, April 18, crews plan to pothole for upcoming work. Thursday, April 19, and Friday, April 20, crews are scheduled to work on water main installation at the intersection of Turk.

Turk to Golden Gate: Monday, April 9, through Wednesday, April 11, crews are scheduled to pothole for upcoming work. Monday, April 16, through Friday, April 20, crews are scheduled to install a joint-utility trench at the intersection of Golden Gate. Thursday, April 19, and Friday, April 20, crews are scheduled to work on water main installation at the intersection of Turk.

Golden Gate to McAllister: Monday, April 9, through Friday, April 13, crews are scheduled to work on sewer and water main installation at the intersection of McAllister. Monday, April 16, through Friday, April 20, crews are scheduled to work on sewer main installation. Due to sewer installation work, intensive noise and vibrations are expected at these times. Monday, April 16, through Friday, April 20, crews are scheduled to install a joint utility trench at the intersection of Golden Gate.

Fell to Market: Night work is scheduled Thursday, April 12, and Friday, April 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to assess subsidewalk basements. Night work is also scheduled Monday, April 16, through Friday, April 20, when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.