Van Ness Construction Forecast: April 30 - May 11, 2018

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit sfmta.com/vanness.

The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.

Tentative Schedule:

Lombard to Greenwich: Monday, May 7, through Friday, May 11, crews are scheduled to work on water main installation.

Greenwich to Filbert: Monday, April 30, through Friday, May 4, crews are scheduled to work on sewer and water main installation. Monday, May 7, and Tuesday, May 8, crews are scheduled to work on water main installation.

Filbert to Union: Monday, April 30, through Friday, May 4, and Monday, May 7, through Friday, May 11, crews are scheduled to work on sewer and water main installation. Due to sewer installation work, intensive noise and vibration is expected.

Green to Vallejo: Monday, May 7, through Friday, May 11, crews are scheduled to pothole for upcoming work. Thursday, May 10, and Friday, May 11, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Vallejo to Broadway: Monday, April 30, through Friday, May 4, crews are scheduled to pothole for upcoming work. Monday, April 30, through Friday, May 4, and Monday, May 7, through Friday, May 11, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Washington to Clay: Night work is scheduled Thursday and Friday, May 3 and 4, and Monday through Friday, May 7 through 11 when crews are scheduled to prepare the area for upcoming sewer work.

Clay to Sacramento: Night work is scheduled Thursday and Friday, May 3 and 4, and Monday through Friday, May 7 through 11 when crews are scheduled to prepare the area for upcoming sewer work.

Sacramento to California: Night work is scheduled Thursday and Friday, May 3 and 4, and Monday through Friday, May 7 through 11 when crews are scheduled to prepare the area for upcoming sewer work.

California to Pine: Night work is scheduled Thursday and Friday, May 3 and 4, and Monday through Friday, May 7 through 11 when crews are scheduled to prepare the area for upcoming sewer work.

Pine to Bush: Night work is scheduled Thursday and Friday, May 3 and 4, and Monday through Friday, May 7 through 11 when crews are scheduled to prepare the area for upcoming sewer work.

Bush to Sutter: Night work is scheduled Thursday and Friday, May 3 and 4, and Monday through Friday, May 7 through 11 when crews are scheduled to prepare the area for upcoming sewer work. Monday, May 7, through Wednesday, May 11, crews are also expected to work on the emergency firefighting water system. Disruptive noise is expected.

Sutter to Post: Monday, April 30, through Friday, May 4, crews are scheduled to work on water main installation.

Night work is scheduled Monday, May 7, through Friday, May 11, between the hours of 8:00 p.m. and 7:00 a.m., when crews are expected to work on the emergency firefighting water system. Disruptive noise is expected.

Geary to O'Farrell: Monday, April 30, through Friday, May 4, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Due to sewer main installation, access to Myrtle Street from Van Ness Avenue will be closed temporarily.

Ellis to Eddy: Monday, April 30, through Friday, May 4, and Monday, May 7, through Friday, May 11, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Monday, May 7, through Friday, May 11, crews are also scheduled to pothole for upcoming work.

Night work is scheduled Monday, May 7, through Friday, May 11, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on water main installation at the intersection of Eddy.

Eddy to Turk: Monday, April 30, through Friday, May 4, crews are scheduled to pothole for upcoming work. Tuesday, May 1, through Friday, May 4, and Monday, May 7, crews are scheduled to install a joint-utility trench. Monday, May 7, through Friday, May 11, crews are scheduled to work on sewer main installation and installing post foundations. Intensive noise and vibration is expected.

Night work is scheduled Monday, May 7, through Friday, May 11, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on water main installation at the intersection of Eddy.

Golden Gate to McAllister: Monday, April 30, and Tuesday, May 8, through Friday, May 11, crews are scheduled to install a joint-utility trench.

Monday, April 30, through Friday, May 4, materials are scheduled for delivery between the hours of 8:00 p.m. and 7:00 a.m. Night work is scheduled Monday, May 7, through Friday, May 11, between the hours of 8:00 p.m. and 7:00 a.m., when crews are expected to work on the emergency firefighting water system. Disruptive noise is expected.

Fell to Market: Night work is scheduled Monday, April 30, through Friday, May 4, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on the emergency firefighting water system. Disruptive noise is expected.

Mission: Night work is scheduled Thursday, May 3, through Friday, May 4, and Monday, May 7, through Thursday, May 10, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on the emergency firefighting water system. Disruptive noise is expected.