FINAL UPDATE: Delay at Powell Station has cleared. IB/OB #subwaysvc resuming normal operations. (More: 31 in last 48 hours)

This page has older content

Please see Related Projects on this page for current project information. We are keeping this page as a record of SFMTA outreach.

Van Ness Construction Forecast: May 7 - May 18, 2018

 

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit sfmta.com/vanness.

The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.

Tentative Schedule:

Lombard to Greenwich: Monday, May 7, through Friday, May 11 crews are scheduled to work on water main installation. Monday, May 14, through Friday, May 18, crews are scheduled to work on sewer and water main installation. Due to sewer installation work, intensive noise and vibration is expected.

Greenwich to Filbert: Monday, May 7, through Wednesday, May 9, crews are scheduled to work on water main installation.

Night work is scheduled Monday, May 14, through Friday, May 18, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Filbert to Union: Monday, May 7, through Friday, May 11, and Monday, May 14, through Friday, May 18, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Night work is scheduled Monday, May 14, through Friday, May 18, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Union to Green: Monday, May 7, through Friday, May 11, and Monday, May 14, through Friday, May 18, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Monday, May 14, through Friday, May 18, crews are also scheduled to pothole for upcoming work.

Green to Vallejo: Monday, May 7, through Friday, May 11, and Monday, May 14, through Wednesday, May 16, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Monday, May 7, through Friday, May 11, crews are also scheduled to pothole for upcoming work.

Broadway: Monday, May 14, through Friday, May 18, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Night work is scheduled Monday, May 7, through Friday, May 11, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Jackson to Washington: Night work is scheduled Monday, May 7, through Friday, May 11, and Monday, May 14, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm utilities for upcoming sewer work. Night work is also scheduled Thursday, May 17, and Friday, May 18, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.

Washington to Clay: Night work is scheduled Thursday, May 10, through Friday, May 11, and Monday, May 14, through Friday, May 18, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm utilities and prepare the area for upcoming sewer work.

Clay to Sacramento: Night work is scheduled Monday, May 7, through Friday, May 11, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work. Night work is also scheduled Tuesday, May 15, through Friday, May 18, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm utilities for upcoming sewer work.

California to Pine: Night work is scheduled Monday, May 7, through Friday, May 11, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.

Bush to Sutter: Night work is scheduled Monday, May 7, through Wednesday, May 9, between the hours of 8:00 p.m. and 7:00 a.m., crews are expected to work on the emergency firefighting water system. Disruptive noise is expected. Night work is also scheduled Monday, May 7, through Friday, May 11, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.

Sutter to Post: Night work is scheduled Monday, May 7, through Friday, May 11, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on updating the emergency firefighting water system and to prepare the area for upcoming sewer work. Disruptive noise is expected.

Geary to O'Farrell: Monday, May 7, through Friday, May 11, and Monday, May 14, through Friday, May 18, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Ellis to Eddy: Monday, May 7, through Friday, May 11, and Monday, May 14, through Friday, May 18, crews are scheduled to work on water and sewer main installation. Due to sewer installation work, intensive noise and vibration is expected.

Night work is scheduled Monday, May 7, through Friday, May 11, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on water main installation at the intersection of Eddy.

Eddy to Turk: Monday, May 7, through Friday, May 11, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Due to sewer main installation, access to Larch Street from the west side of Van Ness Avenue will be closed temporarily. Monday, May, 14, through, Friday, May 18, crews are scheduled to work on sewer and water main installation, and on installing a joint-utility trench. Due to sewer installation work, intensive noise and vibration is expected.

Night work is scheduled Monday, May 7, through Friday, May 11, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on water main installation at the intersection of Eddy.

Golden Gate to McAllister: Monday, May 7, through Friday, May 11, and Monday, May 14, through Friday, May 18, crews are scheduled to install a joint-utility trench.

Night work is scheduled Monday, May 7, through Friday, May 11, between the hours of 8:00 p.m. and 7:00 a.m., when crews are expected to work on updating the emergency firefighting water system. Disruptive noise is expected.

Grove to Hayes: Night work is scheduled Thursday, May 10, through Friday, May 11, and Monday, May 14, through Friday, May 18, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm utilities for upcoming sewer work.

Fell to Market: Night work is scheduled Monday, May 7, through Friday, May 11, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm utilities for upcoming sewer work. Night work is scheduled Friday, May 11, and Monday, May 14, through Thursday, May 17, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on updating the emergency firefighting water system. Disruptive noise is expected.

Market to Mission: Night work is scheduled Monday, May 7, through Friday, May 11, and Monday, May 14, through Thursday, May 17, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on updating the emergency firefighting water system. Disruptive noise is expected.