Van Ness Avenue Construction Forecast: June 25 - July 6, 2018

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit

 

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit sfmta.com/vanness.

The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.

Tentative Schedule:

Lombard Avenue to Mission Street: Monday, June 25, through Friday, June 29, Monday and Tuesday, July 2 and 3, and Thursday and Friday, July 5 and 6, crews are expected to prepare the median on Van Ness Avenue for upcoming work.

Northpoint to Bay: Thursday, June 28, Friday, June, 29, and Monday, July 2, crews are scheduled to pothole for upcoming work.

Bay to Francisco: Tuesday, July 3, Thursday, July 5, and Friday, July 6, crews are scheduled to pothole for upcoming work.

Lombard to Greenwich: Monday, June 25, through Friday, June 29, Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday July 6, crews are scheduled to work on water main installation. Thursday, July 5, and Friday, July 6, crews are also scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Night work is scheduled Monday, June 25, through Friday, June 29, Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday July 6, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Filbert: Monday, June 25, through Friday, June 29, crews are scheduled to work on water main installation.

Green to Vallejo: Monday, June 25, through Friday, June 29, Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday July 6, crews are scheduled to work on roadway restoration.

Pacific to Jackson: Monday, June 25, through Friday, June 29, Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday July 6, crews are scheduled to work on sewer and water main installation. Due to sewer installation work, intensive noise and vibration is expected.

Sutter: Monday, June 25, through Friday, June 29, Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday July 6, crews are scheduled to work on water main installation.

Post to Geary: Monday, June 25, through Friday, June 29, Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday July 6, crews are scheduled to work on sewer  and water main installation. Due to sewer work, intensive noise and vibration is expected.

Night work is scheduled Wednesday, June 27, through Friday, June 29, Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday July 6, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on water main installation.

O’Farrell to Ellis: Monday, June 25, through Friday, June 29, Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday July 6, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Thursday, July 5, through Friday July 6, crews are also scheduled to install a joint-utility trench and to pothole for upcoming work.

Night work is scheduled Monday, June 25, through Friday, June 29, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on water main installation.

Ellis to Eddy: Monday, June 25, through Friday, June 29, Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday July 6, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Crews are also scheduled to install a joint-utility trench and pothole for upcoming work.

Night work is scheduled Monday, June 25, through Friday, June 29, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on water main installation.

Eddy to Turk: Monday, June 25, through Friday, June 29, Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday July 6, crews are scheduled to work on sewer main installation and to install a joint-utility trench. Due to sewer work, intensive noise and vibration is expected. Monday, June 25, through Thursday, June 28, crews are also scheduled to pothole for upcoming work.

Turk to Golden Gate: Monday, June 25, through Friday, June 29, and Monday, July 2, through Tuesday, July 3, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday July 6, crews are also scheduled to install a joint-utility trench.

Night work is scheduled Monday, June 25, through Friday, June 29, Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday July 6, between the hours of 8:00 p.m. and 7:00 a.m., when crews are expected to work on updating the emergency firefighting water system. Disruptive noise is expected.

Golden Gate to McAllister: Monday, June 25, through Friday, June 29, Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday July 6, crews are scheduled to work on roadway restoration.

McAllister to Grove: Night work is scheduled Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday July 6, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.

Grove to Hayes: Night work is scheduled Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday July 6, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.

Hayes to Fell: Night work is scheduled Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday July 6, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.

Fell to Market: Thursday, July 5 and Friday, July 6 crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Night work is scheduled Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday July 6, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.

Market to Mission: Night work is scheduled Monday, June 25, through Friday, June 29, Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday July 6, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities and to prepare the area for upcoming sewer work.