Van Ness Avenue Construction Forecast: July 9 - July 20, 2018

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit sfmta.com/vanness.

The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.

Tentative Schedule:

Lombard to Greenwich: Monday, July 16, through Friday, July 20, crews are scheduled to work on sewer main installation and permitted sidewalk tree stump removal.

Night work is scheduled Monday, July 9, through Friday, July 13, and Monday, July 16, through Friday, July 20, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer and water main installation. Disruptive noise is expected. Night work is also scheduled Tuesday, July 10, through Wednesday, July 11, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.

Greenwich to Filbert: Monday, July 16, through Wednesday, July 18, crews are scheduled to complete permitted sidewalk tree stump removal.

Night work is scheduled Tuesday, July 10, through Wednesday, July 11, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.

Filbert to Union: Monday July 9, through Friday, July 13, and Tuesday, July 17, through Friday, July 20, crews are scheduled to work on water main installation. Monday, July 16, through Wednesday, July 18, crews are also scheduled to complete permitted sidewalk tree stump removal.

Night work is scheduled Tuesday, July 10, through Wednesday, July 11, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.

Union to Green: Monday July 9, through Friday, July 13, and Tuesday, July 17, through Friday, July 20, crews are scheduled to work on water main installation. Monday, July 16, through Wednesday, July 18, crews are also scheduled to complete permitted sidewalk tree stump removal.

Night work is scheduled Monday, July 9, through Wednesday, July 11, and Tuesday, July 17, through Friday, July 20, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.

Green to Vallejo: Monday, July 9, through Friday, July 13, and Monday, July 16, through Friday, July 20, crews are scheduled to work on roadway restoration. Monday, July 16, through Wednesday, July 18, crews are also scheduled to complete permitted sidewalk tree stump removal.

Night work is scheduled Monday, July 9, through Wednesday, July 11, and Tuesday, July 17, through Friday, July 20, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.

Vallejo to Broadway: Monday, July 16, through Wednesday, July 18, crews are scheduled to complete permitted sidewalk tree stump removal.

Night work is scheduled Monday, July 9, through Friday, July 13, and Monday, July 16, through Friday, July 20, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.

Broadway to Pacific: Monday July 9, through Friday, July 13, and Monday, July 16, through Friday, July 20, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Monday, July 16, through Wednesday, July 18, crews are also scheduled to complete permitted sidewalk tree stump removal.

Night work is scheduled Monday, July 9, through Friday, July 13, and Monday, July 16, through Friday, July 20, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.

Pacific to Jackson: Monday July 9, through Friday, July 13, and Monday, July 16, through Friday, July 20, crews are scheduled to work on sewer and water main installation. Due to sewer work, intensive noise and vibration is expected. Monday, July 16, through Wednesday, July 18, crews are also scheduled to complete permitted sidewalk tree stump removal.

Night work is scheduled Monday, July 9, through Friday, July 13, and Monday, July 16, through Friday, July 20, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities and to prepare the area for upcoming sewer work.

Jackson to Washington: Monday, July 16, through Wednesday, July 18, crews are scheduled to complete permitted sidewalk tree stump removal.

Night work is scheduled Monday, July 9, through Friday, July 13, and Monday, July 16, through Friday, July 20, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities and to prepare the area for upcoming sewer work.

Washington to Clay: Night work is scheduled Monday, July 16, through Friday, July 20, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.

Clay to Sacramento: Night work is scheduled Monday, July 16, through Friday, July 20, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.

Sacramento to California: Night work is scheduled Monday, July 16, through Friday, July 20, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.

California to Pine: Night work is scheduled Monday, July 16, through Friday, July 20, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.

Pine to Bush: Night work is scheduled Monday, July 16, through Friday, July 20, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.

Bush to Sutter: Night work is scheduled Monday, July 16, through Friday, July 20, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.

Sutter to Post: Monday, July 9, and Tuesday, July 17, through Friday, July 20, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Monday, July 16, through Wednesday, July 18, crews are also scheduled to complete permitted sidewalk tree stump removal.

Night work is scheduled Tuesday, July 10, through Friday, July 13, and Monday, July 16, through Friday, July 20, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Geary to O'Farrell: Monday, July 9, through Friday, July 13, and Monday, July 16, through Friday, July 20, crews are scheduled to work on sewer installation and to pothole for upcoming work. Due to sewer work, intensive noise and vibration is expected. Monday, July 16, through Friday, July 20, crews are also scheduled to install a joint-utility trench and to complete permitted sidewalk tree stump removal.

Night work is scheduled Monday July 9, through Friday, July 13, and Monday, July 16, through Friday, July 20, between the hours of 8:00 p.m. and 7:00 a.m., when crews are expected to work on updating the emergency firefighting water system. Disruptive noise is expected.

O’Farrell to Ellis: Monday July 9, through Friday, July 13, and Monday, July 16, through Friday, July 20, crews are scheduled to work on sewer main installation, to install a joint-utility trench and to pothole for upcoming work. Due to sewer work, intensive noise and vibration is expected. Monday, July 16, through Wednesday, July 18, crews are also scheduled to complete permitted sidewalk tree stump removal.

Ellis to Eddy: Monday July 9, through Friday, July 13, and Monday, July 16, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Monday, July 16, through Friday, July 20, crews are scheduled to install a joint-utility trench, to work on roadway restoration and to complete permitted sidewalk tree stump removal.

Eddy to Turk: Monday July 9, through Friday, July 13, crews are scheduled to install a joint-utility trench. Monday, July 16, through Wednesday, July 18, crews are scheduled to complete permitted sidewalk tree stump removal.

Turk to Golden Gate: Monday July 9, through Friday, July 13, and Monday, July 16, through Friday, July 20, crews are scheduled to install a joint-utility trench and to work on roadway restoration. Monday July 9, through Friday, July 13, and Monday July 16, through Tuesday, July 17, crews are also scheduled to work on updating the emergency firefighting water system. Monday, July 16, through Wednesday, July 18, crews are also scheduled to complete permitted sidewalk tree stump removal.

Golden Gate to McAllister: Monday, July 9, through Friday, July 13, and Monday, July 16, through Friday, July 20, crews are scheduled to work on roadway restoration. Thursday, July 12, traffic lanes on Van Ness and South Van Ness avenues between Mission and McAllister streets will shift to extend the southern construction zone south from Sutter to Mission streets.

Night work is scheduled Monday, July 9, through Friday, July 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.

McAllister to Grove: Thursday, July 12, traffic lanes on Van Ness and South Van Ness avenues between Mission and McAllister streets will shift to extend the southern construction zone south from Sutter to Mission streets. Thursday, July 18, through Friday, July 20, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Night work is scheduled Monday, July 9, through Friday, July 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.

Grove to Hayes: Thursday, July 12, traffic lanes on Van Ness and South Van Ness avenues between Mission and McAllister streets will shift to extend the southern construction zone south from Sutter to Mission streets. Wednesday, July 18, through Friday, July 20, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Night work is scheduled Monday, July 9, through Friday, July 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.

Hayes to Fell: Thursday, July 12, traffic lanes on Van Ness and South Van Ness avenues between Mission and McAllister streets will shift to extend the southern construction zone south from Sutter to Mission streets.

Night work is scheduled Monday, July 9, through Friday, July 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.

Fell to Market: Thursday, July 12, traffic lanes on Van Ness and South Van Ness avenues between Mission and McAllister streets will shift to extend the southern construction zone south from Sutter to Mission streets.

Night work is scheduled Monday, July 9, through Friday, July 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.

Market to Mission: Thursday, July 12, traffic lanes on Van Ness and South Van Ness avenues between Mission and McAllister will shift to extend the southern construction zone south from Sutter to Mission streets.

Night work is scheduled Monday, July 9, through Friday, July 13 and Monday, July 16, through Friday, July 20, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area and to pothole to confirm underground utilities for upcoming sewer work.