Van Ness Avenue Construction Forecast: July 30 - August 10, 2018

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit sfmta.com/vanness.

The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.

Tentative Schedule:

Lombard to Greenwich: Monday through Friday, July 30 through August 3, crews are scheduled to perform water work.

Night work is scheduled Monday through Friday, August 6 through August 10, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation. Disruptive noise is expected.

Greenwich to Filbert: Monday through Friday, August 6 through August 10, crews are scheduled to pothole for upcoming work.

Filbert to Union: Monday through Friday, July 30 through August 3, crews are scheduled to pothole for upcoming work. Monday through Wednesday, August 6 through August 8, crews are scheduled to perform water work.

Broadway to Pacific: Night work is scheduled Monday through Friday, July 30 through August 3, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.

Jackson to Washington: Night work is scheduled Monday through Friday, August 6 through August 10, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole and to prepare the area for upcoming sewer work.

Washington to Clay: Thursday, August 9, and Friday, August 10, crews are scheduled to prepare the area for upcoming sewer work.

Night work is scheduled Monday through Friday, August 6 through August 10, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole and to prepare the area for upcoming sewer work.

Clay to Sacramento: Thursday, August 9, and Friday, August 10, crews are scheduled to prepare the area for upcoming sewer work.

Night work is scheduled Monday through Friday, August 6 through August 10, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole and to prepare the area for upcoming sewer work.

Sacramento to California: Night work is scheduled Monday through Friday, August 6 through August 10, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole and to prepare the area for upcoming sewer work.

California to Pine: Saturday, August 4 and Sunday, August 5, crews are scheduled to perform emergency roadway repairs.

Night work is scheduled Monday through Friday, August 6 through August 10, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole and to prepare the area for upcoming sewer work.

Pine to Bush: Night work is scheduled Monday through Friday, August 6 through August 10, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole and to prepare the area for upcoming sewer work.

Bush to Sutter: Monday through Friday, July 30 through August 3, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Night work is scheduled Monday through Friday, August 6 through August 10, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole and to prepare the area for upcoming sewer work.

Sutter to Post: Monday through Friday, July 30 through August 3, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Night work is scheduled Thursday through Friday, August 2 through August 3, and Monday, August, 6, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work. Night work is scheduled Monday through Friday, August 6 through August 10, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation and to prepare the area for upcoming sewer work. Intensive noise and vibration is expected.

Post to Geary: Monday, July 30, crews are scheduled to perform water work.

Night work is scheduled Monday through Friday, July 30 through August 3, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole for upcoming work. Night work is scheduled Monday through Friday, August 6 through August 10, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Geary to O'Farrell: Monday, July 30, crews are scheduled to perform water work.

Night work is scheduled Wednesday, August 1 and Thursday, August 2, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work. Night work is also scheduled Thursday, August 9 and Friday, August 10, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on updating the emergency firefighting water system. Disruptive noise is expected.

O’Farrell to Ellis: Monday through Friday, July 30 through August 3, and Monday through Wednesday, August 6, through August 8, crews are scheduled to install a joint-utility trench.

Night work is scheduled Monday through Thursday, July 31 through August 1, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.

Ellis to Eddy: Monday through Wednesday, July 30, through August 1, crews are scheduled to install a joint-utility trench. Wednesday through Friday, August 8 through August 10, crews are scheduled to work on sidewalk replacement.

Night work is scheduled Monday through Wednesday, July 30 through August 1, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.

Eddy to Turk: Wednesday through Friday, August 8 through August 10, crews are scheduled to perform water work and install a joint-utility trench.

Night work is scheduled Monday through Wednesday, July 30 through August 1, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.

Turk to Golden Gate: Monday through Friday, July 30 through August 3, and Monday through Friday, August 6 through August 10, crews are scheduled to work on sidewalk replacement. Thursday, August 9 and Friday, August 10, crews are also scheduled to install a joint-utility trench,

Night work is scheduled Monday through Wednesday, August 6 through August 8, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on updating the emergency firefighting system and to pothole to confirm underground utilities for upcoming sewer work. Disruptive noise is expected.

Golden Gate to McAllister: Monday, July 30, and Monday through Tuesday, August 6 through August 7, crews are scheduled to perform water work. Monday through Friday, August 6, through August 10, crews are scheduled to work on sidewalk replacement.

McAllister to Grove: Monday through Friday, July 30 through August 3, and Monday through Friday, August 6 through August 8, crews are scheduled to work on sewer main installation and to perform water work. Due to sewer installation work, intensive noise and vibration is expected.

Night work is scheduled Monday through Wednesday, July 30 through August 1, and Monday through Wednesday, August 6 through August 8, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on the overhead contact system.

Grove to Hayes: Monday through Friday, July 30 through August 3, and Monday through Friday, August 6 through August 8, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Monday through Friday, August 6 through August 8, crews are also scheduled to pothole for upcoming work.

Night work is scheduled Monday through Friday, July 30 through August 3, and Monday through Friday, August 6 through August 10, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on the overhead contact system.

Hayes to Fell: Monday through Friday, July 30 through August 3, and Monday through Friday, August 6 through August 10, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Night work is scheduled Thursday through Friday, August 2 through August 3, and Thursday through Friday, August 9 through August 10, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on the overhead contact system.

Fell to Market: Night work is scheduled Thursday through Friday, August 2 through August 3, and Thursday through Friday, August 9 through August 10, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on the overhead contact system.

Market to Mission: Night work is scheduled Thursday through Friday, August 2 through August 3, and Thursday through Friday, August 9 through August 10, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on the overhead contact system.