FINAL UPDATE: Delay at Market and 4th is clearing. IB #FMarket is resuming service. (More: 19 in last 48 hours)

This page has older content

Please see Related Projects on this page for current project information. See Travel & Transit Updates for current travel updates. We are keeping this page as a record of SFMTA service and outreach.

Van Ness Avenue Construction Forecast: September 24 - October 5, 2018

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit SFMTA.com/VanNess.

The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.

Tentative Schedule:

Lombard to Greenwich: Wednesday through Friday, September 26 through September 28, crews are scheduled to work on sewer main installation. Monday through Friday, October 1 through October 5, crews are scheduled to work on sewer main installation and sidewalk replacement.

Greenwich to Filbert: Monday through Friday, October 1 through October 5, crews are scheduled to work on sidewalk replacement.

Filbert to Union: Thursday, September 27 and Friday, September 28, crews are scheduled to perform water work. Monday through Friday, October 1 through October 5, crews are scheduled to work on sidewalk replacement.

Union to Green: Tuesday through Friday, September 25 through September 28, and Monday through Friday, October 1 through October 5, crews are scheduled to work on sidewalk replacement. Thursday, September 27 and Friday, September 28, crews are also scheduled to perform water work.

Vallejo to Broadway: Monday through Friday, September 24 through September 28, and Monday through Friday, October 1 through October 5, crews are scheduled to work on sidewalk replacement.

Broadway to Pacific: Monday through Friday, September 24 through September 28, and Monday through Friday, October 1 through October 5, crews are scheduled to work on sidewalk replacement.

Pacific to Jackson: Monday through Friday, September 24 through September 28, and Monday through Wednesday, October 1 through October 3, crews are scheduled to work on sidewalk replacement.

Jackson to Washington: Monday through Friday, September 24 through September 28, and Monday through Friday, October 1 through October 5, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Pine to Bush: Wednesday through Friday, October 3 through October 5, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Bush to Sutter: Monday through Friday, September 24 through September 28, crews are scheduled to install a joint-utility trench. Wednesday through Friday, October 3 through October 5, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Sutter to Post: Monday through Friday, September 24 through September 28, and Monday through Friday, October 1 through October 5, crews are scheduled to work on sidewalk replacement and to install a joint-utility trench.

Post to Geary: Night work is scheduled Monday through Friday, October 1 to October 5, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on updating the emergency firefighting system. Disruptive noise is expected.

Geary to O'Farrell: Monday through Friday, September 24 through September 28, and Monday through Friday, October 1 through October 5, crews are scheduled to work on sidewalk replacement and to install a joint-utility trench. Monday, September 24 and Tuesday, September 25, crews are also scheduled to pothole for upcoming work.

Night work is scheduled Monday through Friday, September 24 through September 28, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on updating the emergency firefighting system. Disruptive noise is expected and access to Myrtle street from the west side of Van Ness Avenue might be limited.

O'Farrell to Ellis: Monday through Friday, September 24 through September 28, and Monday through Friday, October 1 through October 5, crews are scheduled to work on sidewalk replacement and to install a joint-utility trench.

Ellis to Eddy: Monday through Wednesday, September 24 through September 26, crews are scheduled to work on sidewalk replacement. Wednesday through Friday, October 3 through October 5, crews are scheduled to work on sewer main installation.

Eddy to Turk: Monday through Friday, September 24 through September 28, and Monday through Friday, October 1 through October 5, crews are scheduled to work on sidewalk replacement and sewer main installation.

McAllister to Grove: Monday through Friday, September 24 through September 28, and Monday through Friday, October 1 through October 5, crews are scheduled to work on sewer and water main installation. Intensive noise and vibration is expected.

Grove to Hayes: Monday through Friday, September 24 through September 28, and Monday through Friday, October 1 through October 5, crews are scheduled to install a joint-utility trench. Monday through Friday, October 1 through October 5, crews are also scheduled to work on sewer and water main installation. Intensive noise and vibration is expected.

Hayes to Fell: Monday through Friday, October 1 through October 5, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Fell to Market: Monday through Friday, September 24 through September 28, and Monday through Friday, October 1 through October 5, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.