North Beach Utility Relocation 9/14/12

Construction Update

North Beach Utility Relocation

This week the contractor completed work to relocate an AT&T underground utility line. Construction on a city water line and a sewer manhole is planned to commence next week. This work will require the closure of one lane for northbound traffic. Either the right or left lane will close during construction hours from Monday to Friday. When the left lane is closed, the southbound lanes may be shifted toward the western side of the street. Both southbound lanes will remain open, and traffic controls will be in place to facilitate safe travel through the area. 

Should you have questions about construction or the Central Subway Project, don't hesitate to contact our team. You can reach us at central.subway@sfmta.com or by phone at 415-701-4371.

We appreciate your continued patience while construction is in progress.

-The Central Subway Team
columbus and union with bus

Work Completed Sept. 10-14

This week the contractor has been working to relocate underground AT&T conduit structures on Columbus Avenue between Union and Powell streets. 

Traffic impacts: To accommodate construction, the right lane for northbound traffic was closed during construction hours (7 a.m. to 3:30 p.m.).

Transit impacts: The northbound bus stop on Columbus Avenue at Union Street was closed during construction hours. The 30 Stockton and 8X/8BX Bayshore Express stop here.  union traffic controls

Planned Construction Sept. 17-21

Next week the contractor plans to begin work on an underground water line and a sewer manhole. This work will take place in one northbound lane at a time on Columbus Avenue.

Traffic impacts: Construction will be underway on the northbound side of the street, with either the right or left lane closed during construction hours. Construction hours are 7 a.m. to 3:30 p.m. On the southbound side of the street, the lanes may be shifted to the west. Both southbound lanes will remain open, and traffic controls will be in place.

Transit impacts: The northbound bus stop on Columbus Avenue at Union Street will be closed Monday thru Friday from 7 a.m. to 4 p.m. The 30 Stockton and 8X/8BX Bayshore Express stop here.