FINAL UPDATE: Stalled train is cleared and the southbound #TThird has resumed service. (More: 10 in last 48 hours)

This page has older content

Please see Related Projects on this page for current project information. We are keeping this page as a record of SFMTA outreach.

Central Subway Construction Update 7/2/15

Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to link the north and south corridors of the city, and will provide a direct connection to major retail, sporting and cultural venues while efficiently transporting people to jobs, educational opportunities and other amenities throughout San Francisco.

This is an exciting time as the San Francisco Municipal Transportation Agency's | Central Subway team works to construct a vital transportation link that, when open in 2019, will improve connectivity for the city. Excavation is underway at the future Chinatown Station Central Subway | Project Advancement

July 2 - July 13, 2015

This notice provides a construction update and a look ahead for what to expect in the areas where we are building four new stations along the alignment. You’ll find information about work activities, traffic and transportation impacts taking place over the next two weeks at SoMa, Yerba Buena|Moscone, Union Square and Chinatown.

Construction schedules, bus routes, and stop locations are subject to change due to unforeseen conditions. Signs will be posted at affected stops to advise of service changes.

Our thanks go out to the businesses, residents, shoppers, commuters, and all those who are touched by the Project, for their continued engagement as we work to extend the city's public transportation system.

The Central Subway Team

Installation of sewer line on 4th Street between Brannan and Townsend is moving along Surface Station, Trackwork and Systems For the work along 4th Street between Bryant and King streets, a surface station located between Bryant and Brannan Streets will be built. Besides construction of the surface station, the only visible construction activities will be upgrading utilities and trackwork on 4th Street between the portal at Bryant and the connection with the existing system at King Street.

Major construction activities will occur at the 4th and King streets intersection, where special trackwork will be installed to connect the existing and new rail systems. This work will be scheduled on three-day holiday weekends, with vehicle traffic maintained or detoured during that time.

Current activity on 4th Street are utilities relocation, Muni manhole, and duct bank installation.

Now through July 10, the contractor is performing work on the 36' sewer line at the 4th and King streets intersection between the hours of 9a.m.- 3p.m. No through-traffic available on King Street to I-280. For more information, please see this notice. In addition, the contractor will also be working to remove the existing high water pressure line. Utility work is progressing at the intersection at 4th and King streets. Installation of the 36' sewer line on 4th between Townsend and King streets       Overview

  • Installation of Muni manhole and duct bank
  • Utility installation
  • 36' sewer line

Details

What: Installation of Muni manhole, duct bank, and utility installation
Time: 7a.m.-4p.m.
When: Monday to Friday
Where: Brannan to King ; 4th and Bryant; Brannan and 4th

What: 36' sewer line
Time: 9a.m.-3p.m.
When: Monday to Friday
Where: Intersection at 4th and King What to expect

  • Work may involve saw-cutting, potholing and jack-hammering on the roadway and sidewalk
  • Sidewalk access may be limited
  • The contractor will maintain a safe path of travel as well as access to businesses during business hours
  • Parking and Traffic Impact
    • Parking will be unavailable along the work area
    • Two lanes on 4th Street between Bryant and King streets are available for traffic

On the west side of 4th Street excavation has begun Yerba Buena | Moscone Station

4th Street from Howard to Folsom

Work along 4th Street between Howard and Folsom streets consists of construction of the underground Yerba Buena | Moscone Station. The cut and cover method known as a "top-down" or "bottom-up" approach involves construction of a box frame structure within a trench excavation that is subsequently backfilled.

Current activity includes excavation, roof deck installation, and utility relocation.

Workers continue to install sewer pipe line on the east side of the roof deck Utility pipes being installed on the east side of the future Yerba Buena | Moscone Station Overview

  • Installation of utilities
  • Excavation and installation of the roof deck

Details

What: Excavation and roof deck installation
Time: 7a.m.-7p.m.
When: Monday to Friday
Where: Howard to Folsom

What: Utility night work
Time: Folsom Street work begins at 9p.m.-5a.m.; Howard Street work begins 6p.m.-5a.m.
When: Monday to Friday
Where: 4th and Folsom and 4th and Howard What to expect

  • Clementina Street is closed at 4th Street
  • The sidewalk on the west side of 4th Street is closed
  • Parking and Traffic Impact
    • One lane will be available on the west side of 4th Street
    • Two right lanes on Folsom Street available during night work

Demolition is ongoing at the northwest corner of the Union Square Garage for the future entrance to the Union Square | Market Street Station Union Square | Market Street Station

For the duration of the project, you'll see work along Stockton Street between Ellis and Post streets. The construction of an underground Union Square|Market Street Station uses the cut and cover method known as a "top-down" or "bottom-up" approach involves construction of a box frame structure within a trench excavation that is subsequently backfilled.

Current activity includes roof deck installation, demolition of the northwest corner of the Union Square Garage, utility relocation, compensation, and jet grouting.

Monday, July 6 and Tuesday, July 7, Geary Boulevard between Grant and Powell is closed to through traffic during night work hours of 9p.m. to 5a.m. The outbound 38 Geary bus stops on Geary at Kearny and at Powell streets will not be in service during schedule night work. Please use alternate bus stops at Market and Montgomery streets or Geary and Taylor.

Single-lane will start on Monday, July 6 on Geary at Stockton to begin pile installation. This activity is estimated to be ongoing through early October 2015.

Demolition of the Union Square Garage continues Southwest facing view of the demolition of the partial Union Square Garage Overview

  • Sheet pile installation
  • Installation of roof deck
  • Utility relocation and support
  • Excavation
  • Compensation and jet grouting
  • Partial demolition of Union Square Garage

Details

What: Pile installation
Time: 9p.m. to 5a.m.
When: Monday and Tuesday (July 6 and July 7)
Where: Stockton and Geary

What: Roof deck, utility, excavation, compensation and jet grouting and partial demolition of Union Square Garage
Time: 7a.m.-11p.m.
When: Monday to Saturday
Where: Ellis to Post
* Construction hours may be 24 hours a day, Monday to Saturday, Sunday work may be required What to expect

  • Local deliveries may access Maiden Lane from Post Street
  • Sidewalk access may be limited at times
  • Muni Service Impact
    • The bus stop for the 38 Geary Route on Geary Boulevard at Stockton Street is discontinued until further notice. Board bus on Geary Boulevard at Powell Street.
    • On Monday and Tuesday, July 6 and July 7, the outbound 38 Geary route between Kearny and Mason streets rerouted during night work hours
      • Bus stops on Geary Boulevard at Kearny and at Powell streets will not be in use during detoured hours of 9p.m. to 5a.m. Use alternate bus stops at Market and Montgomery or Geary Boulevard and Taylor Street
  • Parking and Traffic Impact
    • Ellis Street is closed to through traffic between Stockton and mid-block until late August
    • O'Farrell Street will be narrowed to one lane at Stockton Street until late July
    • Stockton Street between Ellis and Post streets is closed to vehicular traffic

Excavating under the roof deck at the future Chinatown Station Chinatown Station The construction of an underground Chinatown Station uses the sequential excavation method (SEM) along Washington and Stockton streets. The SEM provides a high degree of flexibility during construction and makes it possible to control virtually all kinds of ground conditions, thereby greatly reducing the risks of construction. This method of tunnel construction is used worldwide for small to large openings in a variety of ground types ranging from rock to soil.

Sprayed concrete (shotcrete) and other supporting elements immediately after exposure, followed by installation of additional steel and shotcrete support elements until a safe stable opening is created will be used.

Utility relocation, traffic re-routing, and transit impacts on Stockton Street is expected as work continues between Sacramento and Jackson.

Tentative: Work to install dewatering wells is anticipated to begin next week on Stockton Street between Sacramento to Washington streets. No through traffic at well drilling locations between the hours of 9p.m. to 5a.m.except for Muni buses. Please follow detour signage. During work hours the mid-block bus stop on the west side of Stockton Street between Sacramento and Clay streets will be relocated just south of Sacramento. Excavating the station site at Stockton and Washington PG&E work to reconstruct underground utilities  Overview

  • PG&E reconstructing underground utilities
  • Excavation of station site
  • Installation of dewatering wells

Details

What: PG&E activity
Time: 9a.m. to 3p.m. and 7a.m. to 6p.m.
When: Monday to Friday and Saturday
Where: Washington and Jackson

What: Excavation of station site
Time: 7a.m.-7p.m.
When: Monday to Saturday
Where: Stockton and Washington

What: Dewatering wells installation
Time: 9p.m. to 5a.m.
When: Monday to Friday
Where: Sacramento to Washington What to expect

  • Sidewalk access may be limited at times
  • Muni Service Impact
    • A mid-block bus stop on the west side of Stockton Street between Sacramento and Clay will be relocated just south of Sacramento
    • A bus stop for southbound 8/8AX/8BX Bayshore Express, 30 Stockton, 45 Union/Stockton and 91 Owl on Stockton Street between Washington and Jackson streets is relocated to the north of Jackson Street on Stockton Street
  • Parking and Traffic Impact
    • Detour will be in place between the hours of 9p.m. to 5a.m. during dewatering wells installation
    • Parking will be unavailable during PG&E, water line and potholing work
    • Washington Street:
      • remains closed between Stockton and Trenton streets
      • is converted into a two-way street between Powell Street and the construction zone

Connecting People. Connecting Communities.

Contact Us: If you have questions about construction or the Central Subway Project you can email us at central.subway@sfmta.com or call us at 415-701-4371.

For More Information: The Central Subway team posts frequent project updates on a variety of social media outlets. To find out more about the project and construction progress, follow us on Facebook, Twitter, or Flickr, and check out our blog.

Construction schedules are subject to change.