North Beach Utility Relocation 9/7/12

Construction Update

North Beach Utility Relocation

Next Thursday, September 13, the contractor plans to begin installing a sewer manhole within the Central Subway construction zone in North Beach. To accommodate this work, a new traffic configuration will be in place on Columbus Avenue between Union and Powell streets. While manhole installation is underway, the left lane for northbound traffic will be closed during construction hours. The new traffic configuration will not impact traffic on Union Street, and the westbound bus stop at Union and Columbus will return to its regular location.

From Monday to Wednesday (September 10-12), the contractor expects to continue working on underground AT&T lines. The right lane for northbound traffic will be closed during construction hours while this work is in progress.

Should you have questions about construction or the Central Subway Project, don't hesitate to contact our team. You can reach us at central.subway@sfmta.com or by phone at 415-701-4371.

We appreciate your continued patience while construction is in progress.

-The Central Subway Team
union street crosswalk with traffic control

Work Completed Sept. 3-7

This week the contractor has been working to relocate underground Muni and AT&T conduit structures on Columbus Avenue between Union and Powell streets. 

Traffic impacts: To accommodate construction, the right lane for northbound traffic was closed during construction hours (7 a.m. to 3:30 p.m.). Work was also underway within the intersection of Columbus and Union. Traffic controls were in place, but no lanes on Union Street were closed.

Transit impacts: On work days from 7 a.m. to 4 p.m., the northbound bus stop on Columbus Avenue at Union Street was closed, and the westbound bus stop on Union Street at Columbus Avenue was temporarily relocated to the middle of the block, approximately 100 feet to the east of its regular location. 
construction and pedestrians

Planned Construction Sept. 10-14

For the first part of next week, the contractor will continue working to relocate underground AT&T lines. Starting Thursday, the contractor expects to begin installing a sewer manhole at a new location within the construction zone. 

Traffic impacts: From Monday to Wednesday, the right lane for northbound traffic will be closed during construction hours. On Thursday and Friday, the left lane for northbound traffic on Columbus Avenue will be closed during construction hours. Construction hours are 7 a.m. to 3:30 p.m. 

Transit impacts: The northbound bus stop on Columbus Avenue at Union Street will be closed Monday thru Friday from 7 a.m. to 4 p.m. The 30 Stockton and 8X/8BX Bayshore Express stop here.