Van Ness Avenue Construction Forecast: August 3- August 16, 2019

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit
Walking

Tentative schedule: 

In the next two weeks crews are scheduled to work on water main installation, sidewalk replacement, restoring the street base, paving, installing a joint-utility trench, installing light poles, street light conduits, tree removals and potholing for upcoming work.

The work listed below is scheduled for daytimes, 7:00 a.m. to 8:00 p.m. Planned night work is italicized. The night shift for construction is 8:00 p.m. to 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit SFMTA.com/VanNess.

Saturday August 3

  • Greenwich to Filbert
  • Filbert to Union

Monday through Friday, August 5 through August 9

  • Lombard to Greenwich
  • Greenwich to Filbert Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. *Intensive noise and vibration is expected.
  • Filbert to Union Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. *Intensive noise and vibration is expected.
  • Union to Green *Intensive noise and vibration is expected.
  • Green to Vallejo
  • Vallejo to Broadway
  • Broadway to Pacific
  • Pacific to Jackson
  • California to Pine
  • Pine to Bush (Monday through Wednesday only) Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. *Intensive noise and is expected.
  • Bush to Sutter (Monday through Wednesday only) Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. *Intensive noise and is expected.
  • Sutter to Post (Monday through Wednesday only) Night work is also scheduled Monday through Wednesday, between the hours of 8:00 p.m. and 7:00 a.m. *Intensive noise and is expected.
  • Geary to O'Farrell (Monday through Wednesday only) *Intensive noise and vibration is expected
  • O'Farrell to Ellis *Intensive noise and vibration is expected
  • Ellis to Eddy *Intensive noise and vibration is expected
  • Eddy to Turk *Intensive noise and vibration is expected
  • Turk to Golden Gate *Intensive noise and vibration is expected
  • Golden Gate to McAllister *Intensive noise and vibration is expected
  • Hayes to Fell (Wednesday and Thursday only) *Intensive noise is expected
  • Fell to Market (Monday through Thursday only) *Intensive noise is expected
  • Market to Mission Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. *Intensive noise is expected.
  • Mission to Howard Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. *Intensive noise is expected. Tree removals taking place Monday through Friday beginning at 5:00 a.m.

Saturday, August 10

  • Greenwich to Filbert *Intensive noise and vibration is expected.
  • Filbert to Union *Intensive noise and vibration is expected.
  • Union to Green *Intensive noise and vibration is expected.

Monday through Friday, August 12 through August 16

  • North Point to Bay (Monday through Wednesday only)
  • Francisco to Chestnut (Thursday and Friday only)
  • Greenwich to Filbert Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. *Intensive noise and vibration is expected.
  • Filbert to Union Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. *Intensive noise and vibration is expected.
  • Union to Green *Intensive noise and vibration is expected.
  • Washington to Clay (Monday only) *Intensive noise is expected
  • Clay to Sacramento (Monday only) *Intensive noise is expected
  • Sacramento to California (Monday only)*Intensive noise is expected
  • California to Pine *Intensive noise is expected
  • Sutter to Post *Intensive noise and vibration is expected
  • Post to Geary *Intensive noise and vibration is expected
  • Geary to O'Farrell *Intensive noise and vibration is expected
  • O'Farrell to Ellis *Intensive noise and vibration is expected
  • Ellis to Eddy *Intensive noise and vibration is expected
  • Eddy to Turk *Intensive noise and vibration is expected
  • Fell to Market
  • Market to Mission Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m *Intensive noise is expected
  • Mission to Howard Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m *Intensive noise is expected

Paving work along Van Ness Avenue.