L Taraval Improvement Project Work Forecast Nov. 11 - 27, 2019

Work Forecast Plan for the Weeks of November 11 to November 27, 2019

 
 

Details of Work to be Performed:

  • Continuation of sewer main replacement is planned for the weeks of November 11-15, November 18-22 and November 25-27 between 45th and 40th Avenue.
  • Excavation of small exploratory holes to verify the locations of existing underground waterline is planned for November 11 between 46th and 45th Avenue.

What to Expect:

 

Excavation requires jackhammering of the pavement. Heavy vibrations from the shoring and sheet piling work is expected for the entire duration of sewer main replacement.

Dust control measures will be in place to prevent dust kick up from the work.

Location and Time of Work:

Northside of Taraval Street between 46th and 40th Avenue;

Monday to Friday 7:00 a.m. to 5:00 p.m.

Crews will work on Veterans Day, Monday, November 11, 2019

No work on Thursday, November 28 and Friday, November 29, 2019

Traffic Impacts:

Some parking will be temporarily restricted in construction zones and traffic lanes will be modified in the northbound lane during active work.

From Wednesday, November 13 to Thursday, November 14, parking will be restricted on the west side of Lower Great Highway between Taraval and Santiago and approximately 50 feet between Taraval and Ulloa Street during construction hours for soil off haul.

Muni customer Impacts:

None

 

The following three-week construction forecast is subject to change due to weather delays or unexpected field conditions.

Questions or concerns? Contact us at LTaravalProject@SFMTA.com or 415.646.2382

To view a map of temporary bus stop relocations citywide, please visit: SFMTA.com/TempStopMap

 

Stay Up To Date: For L Taraval Improvement Project work forecast and updates, please sign-up for email updates by visiting LTaravalProject/SFMTA.com.