L Taraval Improvement Project Work Forecast August 8 - August 23, 2020

Neighborhoods Affected
Route(s) Affected

Work Forecast Plan for the Weeks of August 8 to August 23, 2020

Details of Work Performed:
  • Continuation of sewer main replacement work is planned for:
    • August 11-14 and August 17-18 between 39th and 38th Avenue (northside)
    • August 13-14 and August 17 between 45th and 44th Avenue (southside)
    • August 10-14 and August 17-18 between 39th and 38th Avenue (northside)
  • Sewer main connection crossing work is planned for the weeks of:
    • August 11-15 and August 17-22 between 46th and 45th Avenue (northside)
    • August 10-14 and August 17-20 between 43rd and 42nd Avenue (northside)
    • August 10-15 and August 17-22 between 37th Avenue and Sunset Boulevard (northside)
    • August 11-15 and August 17-22 between 46th and 45th Avenue (southside)
    • August 10-14 and August 17-20 between 43rd and 42nd Avenue (southside)
    • August 11-15 and August 17-22 between 37th and 36th Avenue (southside)
  • Continuation of sidewalk curb ramp work is planned for:
    • August 14 and August 17-21 between 40th and 39th Avenue (northside)
    • August 14 and August 17-21 between 42nd and 41st Avenue (southside)
    • August 11-13 between 41st and 39th Avenue (southside)
    • August 14 and August 17-21 between 39th and 38th Avenue (southside)
    • August 11-13 between 38th and 36th Avenue (southside)
  • Construction of replacement Muni overhead contact system (OCS) pole's foundation is planned of: 
    • August 13-14 between 41st and 40th Avenue (northside)
    • August 11-12 between 48th and 47th Avenue (southside)
  • Installation of temporary wooden Muni overhead contact system (OCS) pole is planned for:
    • August 11-12 between 48th and 47th Avenue (northside)
    • August 11-12 between 43rd and 42nd Avenue (northside)
    • August 11-12 between 41st and 40th Avenue (northside)
    • August 11-12 between 39th and 38th Avenue (northside)
    • August 11-12 between 37th Avenue and Sunset Boulevard (northside)
  • Removal of existing Muni overhead contact system (OCS) is planned for:
    • August 8-14 between 46th Avenue and Sunset Boulevard (northside)
    • August 8-14 between 46th Avenue and Sunset Boulevard (northside)
    • Starting August 23 at 46th Avenue & Vicente Street and 46th Avenue & Wawona Street
  • Removal of electrical cables is planned for:
    • August 8-10 between 44th and 42nd Avenue
    • August 8-10 between 41st and 40th Avenue
    • August 8-10 between 39th and 38th Avenue
    • August 8-10 between 37th Avenue and Sunset Boulevard
  • Transfer of existing overhead wires to temporary wooden poles is planned for:
    • August 16 at 46th Avenue & Vicente Street and 47th Avenue and Wawona Street
  • Replacement of existing guy span wires is planned for:
    • August 17-21 on 46th Avenue between Taraval and Wawona Street 
    • August 17-21 on 47th Avenue between Vicente and Wawona Street 
    • August 17-21 on Vicente and Wawona Street between 46th and 47th Avenue
What to Expect:

Excavation requires jackhammering of the pavement. Dust control measures will be in place to prevent dust kick up from the work.

Heavy vibrations from the shoring and sheet piling work is expected for open trench work.

Location and Time of Work:
  • Northside of Taraval Street between 48th and 36th Avenue; 
  • Southside of Taraval Street between 48th and 36th Avenue
  • Both sides of 46th Avenue between Taraval and Wawona Street, 47th Avenue between Vicente and Wawona Street, and on both Vicente and Wawona Street between 46th and 47th Avenue
  • Monday to Friday 8:00 a.m to 5:00 p.m.; Saturday to Sunday 8:00 a.m to 5:00 p.m.
Traffic Impacts:

Some parking will be temporarily restricted in construction zones and traffic lanes will be modified during active work. 

Looking Ahead:  Starting Sunday, August 23 to Thursday, September 3, 2020, construction crew will be replacing components of the Muni overhead contact system (OCS) from 10:00 p.m. to 6:00 a.m. on 46th Avenue between Taraval to Wawona Street, Vicente Street between 46th to 47th Avenue, 47th Avenue between Vicente and Wawona Street, and Wawona Street from 47th to 46th Avenue.


The following two-week construction forecast is subject to change due to weather delays or unexpected field conditions.

Questions or concerns? Contact us at LTaravalProject@SFMTA.com or 415.646.2382

Stay Up To Date: For L Taraval Improvement Project work forecast and updates, please sign-up for email updates by visiting LTaravalProject/SFMTA.com.

 

The most important thing that people can do is to follow the Public Health Order to stay home except for essential needs, practice social distancing, wash hands frequently and look out for one another.

Website to Provide Information for Small Businesses

The City has created a one-stop resource for employers and employees outlining all existing resources, contacts for assistance, and to provide updates on the City’s growing response to the business and worker communities. Website: www.oewd.org/covid19.

Shared Spaces Program

Small Business Support

The SFMTA brings your customers to you on Muni, keeps the streets moving and manages the curb space. We know small businesses have many questions right now and we’re here to help you find resources offered by the City and County of San Francisco.

Where do I find information on Small Business Loans and Grants?

Can I move my business outside?*

How do I safely get back to business in the “new normal?”

More information about these and opportunities such as deferring business taxes and licensing fees, accessing free COVID-19 testing for essential employees and resources for self-employed individuals can be found at oewd.org/covid19

*Please note that applications are subject to review based on feasibility and if there are active construction needs in the area.  


☎ 311 (Outside SF 415.701.2311; TTY 415.701.2323) Free language assistance / 免費語言協助 / Ayuda gratis con el idioma / Бесплатная помощь переводчиков / Trợ giúp Thông dịch Miễn phí / Assistance linguistique gratuite / 無料の言語支援 / 무료 언어 지원 / Libreng tulong para sa wikang Filipino / การช่วยเหลือทางด้านภาษาโดยไม่เสียค่าใช้จ่าย / خط المساعدة المجاني على الرقم