FINAL UPDATE: Delay at Powell Station has cleared. IB/OB #subwaysvc resuming normal operations. (More: 31 in last 48 hours)

This page has older content

Please see Related Projects on this page for current project information. We are keeping this page as a record of SFMTA outreach.

Van Ness Improvement Project Construction Forecast: June 14 - June 25, 2021

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit
Walking

Those traveling on the corridor are advised to stay alert and allow more travel time during construction. Polk Street, one block east of Van Ness Avenue, is a recommended alternative for people traveling by bicycle in the area.
 
At times, bus stops along Van Ness Avenue and its side streets need to be relocated to perform construction for the Van Ness Improvement Project. Signage directs riders to temporary stops.

Parking is currently not available on Van Ness Avenue due to construction. Drivers can find parking in private lots or on side streets. Please do not park on sidewalks or in live traffic lanes. This is dangerous and may result in citations.
 
The work listed below is scheduled for daytimes, 7 a.m. to 8 p.m. Planned night work is italicized. The night shift for construction is 8 p.m. to 7 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work. 
 
The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit SFMTA.com/VanNess. In the next two weeks crews are scheduled to work on overhead power installations, traffic signal wiring and hardware installation, light pole setting and related work. 

Monday through Friday, June 14 through June 18

 Traction power cable pull to be performed between Marina Boulevard and Laguna Street.

  • Bay to Francisco. *Disruptive noise is expected.
  • Francisco to Chestnut. *Disruptive noise is expected.
  • Chestnut to Lombard. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m. 
  • Lombard to Greenwich. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m. Street base work scheduled at Greenwich intersection will close intersection at times.
  • Greenwich to Filbert. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m. Street base work scheduled at Greenwich intersection will close intersection at times.
  • Filbert to Union. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m. 
  • Union to Green. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m. 
  • Green to Vallejo. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m. 
  • Vallejo to Broadway. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m. 
  • Broadway to Pacific. *Disruptive noise is expected.  Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m. Street base work scheduled at Pacific intersection will close intersection at times.
  • Pacific to Jackson. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m. Street base work scheduled at Jackson and Pacific intersections will close intersection a times.
  • Jackson to Washington. *Disruptive noise is expected.  Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m. Mid-block paving and street base work scheduled at Jackson and Washington intersections will close intersection at times.
  • Washington to Clay. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m. Mid-block paving work scheduled at Washington and Clay intersections will close intersection at times.
  • Clay to Sacramento.  *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m. Mid-block paving scheduled at Clay and Sacramento intersections will close intersection at times.
  • Sacramento to California. *Disruptive noise is expected. Mid-block paving and street base work scheduled at Sacramento and California intersections will close intersection at times.
  • California to Pine. *Disruptive noise is expected. Mid-block paving and street base work scheduled at California and Pine intersections will close intersection at times.
  • Pine to Bush. *Disruptive noise is expected. Mid-block paving scheduled at Pine intersection will close intersection at times.
  • Bush to Sutter. *Disruptive noise is expected. 
  • Sutter to Post. *Disruptive noise is expected. 
  • Geary to O'Farrell. *Disruptive noise is expected. 
  • O'Farrell to Ellis. *Disruptive noise is expected. 
  • Ellis to Eddy. *Disruptive noise is expected. 
  • Golden Gate to McAllister. *Disruptive noise is expected.  
  • McAllister to Grove. *Disruptive noise is expected. 
  • Hayes to Fell. *Disruptive noise is expected. 
  • Fell to Market. *Disruptive noise is expected.
  • Market to Mission. *Disruptive noise is expected. 

Monday through Friday, June 21 through June 25

Traction power cable pull to be performed between Marina Boulevard and Laguna Street.

  • Bay to Francisco. *Disruptive noise is expected.  
  • Francisco to Chestnut. *Disruptive noise is expected. 
  • Chestnut to Lombard. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m. 
  • Lombard to Greenwich. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m. Mid-block paving scheduled at Lombard and Greenwich intersections will close intersection at times.
  • Greenwich to Filbert. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m. Mid-block paving scheduled at Greenwich will close intersection at times.
  • Filbert to Union. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m. 
  • Union to Green. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m. 
  • Green to Vallejo. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m. Mid-block paving scheduled at Vallejo intersection will close intersection at times.
  • Vallejo to Broadway. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m. Mid-block paving at Broadway and Vallejo intersections will close intersection at times.
  • Broadway to Pacific. *Disruptive noise is expected.  Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m. Mid-block paving at Broadway intersection will close intersection at times.
  • Pacific to Jackson. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m. 
  • Jackson to Washington. *Disruptive noise is expected.  Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m. 
  • Washington to Clay. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m. 
  • Clay to Sacramento. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m. 
  • Sacramento to California. *Disruptive noise is expected. Street base work scheduled at California intersection will close intersection at times.
  • California to Pine. *Disruptive noise is expected. Street base work scheduled at California intersection will close intersection at times.
  • Pine to Bush. *Disruptive noise is expected.
  • Bush to Sutter. *Disruptive noise is expected. 
  • Sutter to Post. *Disruptive noise is expected.
  • O'Farrell to Ellis. *Disruptive noise is expected. Mid-block paving and street base work scheduled at O’Farrell and Ellis intersection will close intersection at times.
  • Ellis to Eddy. *Disruptive noise is expected. Mid-block paving and street base work scheduled at Ellis intersection will close intersection at times.
  • Turk to Golden Gate. *Disruptive noise is expected. Street base work scheduled at Golden Gate intersection will close intersection at times.
  • Golden Gate to McAllister. *Disruptive noise is expected. Street base work scheduled at Golden Gate and McAllister will close intersection a times.
  • McAllister to Grove. *Disruptive noise is expected. Street base work scheduled at Grove and McAllister intersections will close intersections at times.
  • Grove to Hayes. *Disruptive noise is expected. Street base work scheduled at Hayes and Grove intersections will close intersection at times.
  • Hayes to Fell. *Disruptive noise is expected. Street base work scheduled at Hayes intersection will close intersection at times.
  • Fell to Market. *Disruptive noise is expected. 
  • Market to Mission. *Disruptive noise is expected.