Construction Forecast: January 13, 2017 - January 27, 2017

Monday, January 16: Between the hours of 10:00 p.m. Monday and 5:00 a.m. Tuesday, the Overhead Contact System that powers the electric buses will be removed on Van Ness from McAllister to Post streets and on McAllister near Van Ness.

Traffic Advisory: Between the hours of 10:00 p.m. Monday and 5:00 a.m. Tuesday, lane closures may be in effect for construction activity.

Tuesday, January 17: Median work on Van Ness from Eddy to O'Farrell, Geary to Post, Pine to Sacramento, Washington to Pacific, and Broadway to Filbert streets.

Between the hours of 10:00 p.m. Tuesday and 5:00 a.m. Wednesday, the Overhead Contact System that powers the electric buses will be removed on Van Ness from McAllister to Post streets.

Traffic Advisory: In the early morning Tuesday, the number of traffic lanes will be reduced from three to two on Van Ness northbound from Eddy to O'Farrell streets and southbound from Pine to Sacramento streets. Between the hours of 10:00 p.m. Tuesday and 5:00 a.m. Wednesday, additional lane closures may be in effect for construction activity.

Wednesday, January 18: Median work on Van Ness from Golden Gate to Eddy, Ellis to O'Farrell, Geary to Post, Sutter to California, Sacramento to Jackson, and Broadway to Filbert streets.

Between the hours of 10:00 p.m. Wednesday and 5:00 a.m. Thursday, the Overhead Contact System that powers the electric buses will be removed on Van Ness from McAllister to Post streets.

Traffic Advisory: In the early morning Wednesday, the number of traffic lanes will be reduced from three to two on Van Ness northbound from Golden Gate to Eddy streets and southbound from Sutter to Pine streets. Between the hours of 10:00 p.m. Wednesday and 5:00 a.m. Thursday, additional lane closures may be in effect for construction activity.

Thursday, January 19: Median work on Van Ness from Grove to Eddy, Geary to Washington, and Broadway to Filbert streets.

Between the hours of 10:00 p.m. Thursday and 5:00 a.m. Friday, the Overhead Contact System that powers the electric buses will be removed on Van Ness from McAllister to Post streets and on McAllister near Van Ness.

Traffic Advisory: In the early morning Thursday, the number of traffic lanes will be reduced from three to two on Van Ness northbound from Grove to Golden Gate streets and southbound from Geary to Sutter streets. Between the hours of 10:00 p.m. Thursday and 5:00 a.m. Friday, additional lane closures may be in effect for construction activity.

Friday, January 20: Median work on Van Ness from Grove to Golden Gate, Ellis to Sacramento, and Broadway to Filbert streets.

Traffic Advisory: In the early morning Friday, the number of traffic lanes will be reduced from three to two on Van Ness southbound from Ellis to Geary streets.

Sunday, January 22: Between the hours of 10:00 p.m. Sunday and 5:00 a.m. Monday, the Overhead Contact System that powers the electric buses will be removed on Van Ness from Post to Sutter streets.

Traffic Advisory: Between the hours of 10:00 p.m. Sunday and 5:00 a.m. Monday, lane closures may be in effect for construction activity.

Monday, January 23: Median work on Van Ness from Turk to Pine, Jackson to Pacific, and Broadway to Filbert streets.

Between the hours of 10:00 p.m. Monday and 5:00 a.m. Tuesday, the Overhead Contact System that powers the electric buses will be removed on Van Ness from Geary to Sutter and on Post near Van Ness. The roadway on Van Ness northbound at Hayes will also be repainted during these hours.

Traffic Advisory: In the early morning Monday, the number of traffic lanes will be reduced from three to two on Van Ness northbound from Fell to Grove streets and southbound from Turk to Ellis streets. Between the hours of 10:00 p.m. Monday and 5:00 a.m. Tuesday, additional lane closures may be in effect for construction activity.

Tuesday, January 24: Median work on Van Ness from Hayes to Grove, Turk to Sutter, Jackson to Pacific, and Broadway to Filbert streets.

Between the hours of 10:00 p.m. Tuesday and 5:00 a.m. Wednesday, the Overhead Contact System that powers the electric buses will be removed on Eddy near Van Ness. The roadway on Van Ness southbound at Golden Gate will also be repainted during these hours.

Traffic Advisory: In the early morning Tuesday, the number of traffic lanes will be reduced from three to two on Van Ness northbound from Mission to Fell streets and southbound from McAllister to Turk streets. Between the hours of 10:00 p.m. Tuesday and 5:00 a.m. Wednesday, additional lane closures may be in effect for construction activity.

Wednesday, January 25: Median work on Van Ness from Hayes to McAllister, Golden Gate to Geary, and Broadway to Filbert streets.

Between the hours of 10:00 p.m. Wednesday and 5:00 a.m. Thursday, the Overhead Contact System that powers the electric buses will be removed on Van Ness from Eddy to Post streets.

Traffic Advisory: In the early morning Wednesday, the number of traffic lanes will be reduced from three to two on Van Ness southbound from Hayes to McAllister streets. Between the hours of 10:00 p.m. Wednesday and 5:00 a.m. Thursday, additional lane closures may be in effect for construction activity.

Thursday, January 26: Median work on Van Ness from Turk to Ellis and Jackson to Filbert streets.

Between the hours of 10:00 p.m. Thursday and 5:00 a.m. Friday, the Overhead Contact System that powers the electric buses will be removed on Van Ness from Eddy to Post streets.

Traffic Advisory: In the early morning Thursday, the number of traffic lanes will be reduced from three to two on Van Ness southbound from Market to Hayes streets. Between the hours of 10:00 p.m. Thursday and 5:00 a.m. Friday, additional lane closures may be in effect for construction activity.

Friday, January 27: Median work on Van Ness from Hayes to Turk and Jackson to Filbert streets.

Those who travel in and through the area are advised to take alternate routes and plan for delays.

Please note that construction schedules are subject to change due to weather or unforeseen conditions. For more project details, please visit sfmta.com/vanness.

Check out the three-part Van Ness Improvement Project video series to find out more about construction.