Van Ness Construction Forecast: January 28, 2017 - February 10, 2017

The following Van Ness Improvement Project construction forecast is subject to change due to weather conditions or unforeseen conditions. For more project details, please visit sfmta.com/vanness.

Saturday, January 28: Work will occur in the median on Van Ness from Ellis to Geary streets.

Sunday, January 29: Work will occur in the median on Van Ness from Turk to Ellis streets.

Between the hours of 10:00 p.m. Sunday and 5:00 a.m. Monday, the Overhead Contact System that powers the electric buses will be removed on Van Ness from Post to Sutter streets.

Traffic Advisory: Between the hours of 10:00 p.m. Sunday and 5:00 a.m. Monday, some traffic lanes may be closed for construction activity.

Monday, January 30: Work will occur in the median on Van Ness from Grove to McAllister, Golden Gate to Turk, Pine to California, and Jackson to Union streets.

Between the hours of 10:00 p.m. Monday and 5:00 a.m. Tuesday, the Overhead Contact System that powers the electric buses will be removed on Post near Van Ness.

Traffic Advisory: In the early morning Monday, the number of traffic lanes will be reduced from three to two on Van Ness southbound from Market to Hayes streets. Between the hours of 10:00 p.m. Monday and 5:00 a.m. Tuesday, additional lane closures may be in effect for construction activity.

Tuesday, January 31: Work will occur in the median on Van Ness from Sutter to Pine and Jackson to Vallejo streets.

Between the hours of 10:00 p.m. Tuesday and 5:00 a.m. Wednesday, the roadway on Van Ness southbound at Mission and northbound at Lombard will be repainted. Also during these hours, work will occur in the median on Van Ness from Pacific to Broadway and Union to Filbert streets; and the Overhead Contact System that powers the electric buses will be removed on Eddy near Van Ness.

Traffic Advisory: In the early morning Tuesday, the number of traffic lanes will be reduced from three to two on Van Ness southbound from Mission to Market streets. Between the hours of 10:00 p.m. Tuesday and 5:00 a.m. Wednesday, additional lane closures may be in effect for construction activity.

Wednesday, February 1: Work will occur in the median on Van Ness from Sutter to Pine, Jackson to Broadway, and Filbert to Greenwich streets.

Between the hours of 10:00 p.m. Wednesday and 5:00 a.m. Thursday, work will occur in the median on Van Ness from Pacific to Broadway streets. Also during these hours, the Overhead Contact System that powers the electric buses will be removed on Van Ness from Eddy to Post streets.

Traffic Advisory: Between the hours of 10:00 p.m. Wednesday and 5:00 a.m. Thursday, additional lane closures may be in effect for construction activity.

Thursday, February 2: Work will occur in the median on Van Ness from Post to Sutter, Jackson to Broadway, and Filbert to Lombard streets.

Between the hours of 10:00 p.m. Thursday and 5:00 a.m. Friday, work will occur in the median on Van Ness from Sacramento to Clay and Jackson to Pacific streets. Also during these hours, the Overhead Contact System that powers the electric buses will be removed on Van Ness from Eddy to Post streets.

Traffic Advisory: Between the hours of 10:00 p.m. Thursday and 5:00 a.m. Friday, additional lane closures may be in effect for construction activity.

Friday, February 3: Work will occur in the median on Van Ness from Post to Sutter, Washington to Broadway, and Filbert to Lombard streets.

Between the hours of 10:00 p.m. Friday and 5:00 a.m. Saturday, work will occur in the median on Van Ness from Sacramento to Clay streets.

Traffic Advisory: Between the hours of 10:00 p.m. Friday and 5:00 a.m. Saturday, additional lane closures may be in effect for construction activity.

Saturday, February 4: Between the hours of 10:00 p.m. Saturday and 5:00 a.m. Sunday, work will occur in the median on Van Ness from McAllister to Golden Gate streets.

Traffic Advisory: Between the hours of 10:00 p.m. Saturday and 5:00 a.m. Sunday, additional lane closures may be in effect for construction activity.

Sunday, February 5: Between the hours of 10:00 p.m. Sunday and 5:00 a.m. Monday, work will occur in the median on Van Ness from McAllister to Golden Gate streets. Also during these hours, the Overhead Contact System that powers the electric buses will be removed on Van Ness from McAllister to Eddy streets.

Traffic Advisory: Between the hours of 10:00 p.m. Sunday and 5:00 a.m. Monday, additional lane closures may be in effect for construction activity.

Monday, February 6: Work will occur in the median on Van Ness from Geary to Post and Clay to Broadway streets.

Between the hours of 10:00 p.m. Monday and 5:00 a.m. Tuesday, work will occur in the median on Van Ness from Mission to Market streets. Also during these hours, the Overhead Contact System that powers the electric buses will be removed on Van Ness from McAllister to Eddy streets.

Traffic Advisory: Between the hours of 10:00 p.m. Monday and 5:00 a.m. Tuesday, additional lane closures may be in effect for construction activity.

Tuesday, February 7: Work will occur in the median on Van Ness from Geary to Post and Clay to Pacific streets.

Between the hours of 10:00 p.m. Tuesday and 5:00 a.m. Wednesday, the Overhead Contact System that powers the electric buses will be removed on Van Ness from Sutter to Bush streets and on Sutter near Van Ness.

Traffic Advisory: Between the hours of 10:00 p.m. Tuesday and 5:00 a.m. Wednesday, additional lane closures may be in effect for construction activity.

Wednesday, February 8: Work will occur in the median on Van Ness from Ellis to Geary and Clay to Jackson streets.

Between the hours of 10:00 p.m. Wednesday and 5:00 a.m. Thursday, the Overhead Contact System that powers the electric buses will be removed on Van Ness from Sutter to Bush streets and on Sutter near Van Ness.

Traffic Advisory: Between the hours of 10:00 p.m. Wednesday and 5:00 a.m. Thursday, additional lane closures may be in effect for construction activity.

Thursday, February 9: Work will occur in the median on Van Ness from Ellis to Geary and Clay to Jackson streets.

Between the hours of 10:00 p.m. Thursday and 5:00 a.m. Friday, the Overhead Contact System that powers the electric buses will be removed on Van Ness from Sutter to California streets.

Traffic Advisory: Between the hours of 10:00 p.m. Thursday and 5:00 a.m. Friday, additional lane closures may be in effect for construction activity.

Friday, February 10: Work will occur in the median on Van Ness from Turk to Ellis and Sacramento to Jackson streets.

Those who travel in and through the area are advised to take alternate routes and plan for delays.

Please note that construction schedules are subject to change due to weather or unforeseen conditions. For more project details, please visit sfmta.com/vanness.

For more advice on navigating construction, be sure to check out the latest issue of the Van Ness Improvement Project newsletter.