FINAL UPDATE: Delay at Market and 4th is clearing. IB #FMarket is resuming service. (More: 19 in last 48 hours)

This page has older content

Please see Related Projects on this page for current project information. We are keeping this page as a record of SFMTA outreach.

L Taraval Improvement Project Seg B Project Update and Forecast - May 2 - 14, 2022

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit
Walking
Route(s) Affected

 

Details of Work to be performed:

 

L Taraval Improvement Project Update and Forecast

for the weeks of May 2, 2022 – May 14, 2022

Taraval St.

North side of Taraval between 37th Ave. to 26th avenues

5/2/22 – 5/20/22     Sewer line work 32nd St. intersection

5/5/22 – 5/16/22     Sewer line work 32nd to 31st avenues

North side of Taraval St. between 26th to 18th avenues   

4/18/22 – 5/4/22      Sewer work north side at the intersection of 21st Ave.   

4/27/22 - 5/4/22       Sewer work middle of Taraval St. and 21st Ave.

East of 19th Ave.

5/5/2022 – 5/20/22    Water line work from 15th to 18th avenues

5/5/2022 – 5/20/22    Water line work at intersections of 15th, 16th, 17th , 18th avenues

5/23/22 anticipated   19th Ave. and Taraval St.

Taraval St.

South side between 35th to 22nd avenues

4/29/22 – 5/20/22    Sewer work 32nd to 35th avenues

4/27/22 – 5/6/22      Sewer line work between 35th to 34th avenues

4/28/22 – 5/6/22      Sewer line work at the intersection of 22nd Ave. and Taraval St.

18th to 15th avenues

4/29/22 – 5/5/22      Potholing for sewer line work at 22nd Ave. and Taraval St.

15th Ave. between Taraval and Ulloa streets

4/25/22 - 5/13/22      Excavation and installation of waterline north side Ulloa St. between 15th Ave. and Funston St.

Ulloa Street

North side from 15th Ave to Forest Side Ave.

4/25/22 – 5/6/22       Water line work on the north side of Ulloa St. between Forest Side Ave. to 14th Ave.                                                                                                                                    

Temporary staging locations

2/28/22 - 5/4/22       24th Ave. east side between Santiago and Taraval streets

                                      Staging area is approximately 70 ft. long and 10 ft. wide

4/13/-2 – 5/4/22        32nd Ave. east side between Taraval and Ulloa streets

                                       Staging area is approximately 80 ft. long and 10 ft. wide

4/30/22 – 5/13/22     Ulloa St. south side between 15th to 16th avenues

                                       Staging area approximately 50 ft. long and approximately 10 ft. wide

4/21/22 – 5/13/22     Ulloa St. north side from 15th to Funston St.

                                       Staging area is approximately 80 ft. long and 10 ft. wide

4/25/22 – 5/4/22        18th Ave west side from Taraval to Ulloa streets

                                        Staging area is approximately 65 ft. long and 10 ft. wide

4/25/22 – 5/20/22      14th Ave.  west side and Ulloa St. towards Vicente St.

                                         Staging area is 10 ft. wide and approximately 80 ft. long

4/27/22 – 5/11/22      21st Ave Taraval to Santiago streets

                                        Staging area is approximately 70 ft. long and 10 ft. wide

4/28/22 – 5/13/22      35th Ave. west side from Taraval to Ulloa streets

                                        Staging area is approximately 70 ft. long and 10 ft. wide

4/29/22 – 5/28/22       37th Ave. east side from Santiago to Rivera streets

                                         Staging area is 250 ft. long and approximately 10 ft. wide

4/29/22 – 5/20/22      14th Ave. west side from Ulloa to Vicente streets

                                         Staging area is 10 ft. wide and approximately 80 ft. long

Muni Service:

S Shuttle from West Portal to 21st Ave. provided temporary service for the L bus line. DISCONTINUED 4/11/2022

L Shuttle Bus  Will provide service for the L Taraval line between the Embarcadero and SF Zoo until further notice.  

L Taraval segment B construction is now reaching a phase where the rail tracks west of the intersection of Ulloa and Madrone streets must be taken offline to complete construction work.  Work needs to be performed during construction to facilitate the reconstruction of the water and sewer mains as well as replace the tracks and overhead lines. The S shuttle will turn around at West Portal.

What to Expect::

New sewer and water lines

  • During excavation and installation, some driveways may be temporarily inaccessible
  • Excavation requires jackhammering of the pavement. Dust control measures will be in place to prevent dust kick up from the work
  • Heavy vibrations from the shoring and sheet piling work is expected for open trench work

Vehicle traffic

  • Temporary lane closures east of intersection where work will be performed

Ulloa St North side from 15th Ave and Funston St.

East and west side of 15th Ave. between Taraval and Ulloa streets

  • Posted no parking signs for the duration of work
  • Access may be delayed accessing residences, crews will allow safe access during construction
  • Sidewalk open for trenchwork

Temporary staging and construction areas

  • Posting of no parking signs along the staging areas
  • Posting of no parking signs in active construction areas

Time of Work::

Monday through Friday, from 8 a.m. to 5 p.m.

Saturday, May 14, 2022  

Traffic Impacts:

  • Some parking will be temporarily restricted in construction zones
  • Traffic lanes will be modified during active work
  • There will be dedicated flagger(s) to direct traffic and pedestrians
  • Temporarily close lane at intersection with detours

Impacts outside projects:

Public Works                           19th Ave.

Public Utilities Commission   Vicente St., from Wawona St. to 34th Ave.

(PUC)                                       Wawona St., 15th Ave., and on Vicente St. west of 19th Ave.

PGE

Intersection’s 16th, 17th, 29th avenues

Taraval St. and 30th, 33rd ,36th avenues

Anticipated – subject to change

Weekend Work

Saturday, May 14, 2022           Sewer line work between 26th and 20th avenues