L Taraval Improvement Forecast and Project Segment B Update  April 10 - 22, 2023

Route(s) Affected

In the coming weeks, work continues on water lines, as well as on the overhead contact system (OCS) that powers the trains. OCS work has transitioned to underground conduit work to support power to the trains and the new and existing streetlights. Curb ramp work has started with demolition and grading areas in preparation for construction of the new boarding ramps and to upgrade existing boarding ramps. Track work is expected to begin over the next few weeks starting with the rail assembly. Construction teams will be excavating and jackhammering pavement, which may cause vibrations. Materials are also being temporarily staged nearby. Dust control and housekeeping measures are in place at active construction and staging locations. Extreme weather conditions have impacted the construction schedule.

The inbound bus stop at Taraval and 15th has been relocated across the intersection until fall 2024.

General construction hours are Monday to Friday between 8:00 a.m. and 4:00 p.m. Construction schedules are subject to change. “No Parking” signs will be posted in construction and staging areas, and intersections may be closed to through traffic on Taraval Street.

Multiple agencies are performing infrastructure work in the area. This includes work by Public Works on 19th Avenue, Public Utilities Commission at Vicente and Wawona streets and PG&E along Taraval Street.

L Taraval Improvement Project – Segment B

Construction work is scheduled to be performed - April 10 – 22, 2023

Taraval Street

16th to 17th, 19th to 22nd, 24th to 29th, 31st to 33rd avenues: waterline work, excavating and shoring, backfill of service lateral connections

24th to 29th avenues: OCS pole work, foundation, construct underground conduit

27th, 28th, 32nd, 33rd, 34th, 35th avenues: curb ramp work, demolishing and grading, constructing curb ramp

23rd, 24th, 25th, 28th, 29th avenues: traffic signal work, constructing foundation, underground signal and conduit in sidewalk and ramp

Ulloa Street

14th to Funston avenues: water line work, chlorinate and connect segments

Track Work

Wawona Street (planned beginning the week of April 24 in the Wawona staging area)

21st to 23th avenues: track assembly work, flash butt welding

Temporary staging locations

16th Avenue west side from Taraval to Ulloa streets

17th Avenue west side from Taraval to Santiago streets

17th Avenue east side from Taraval to Santiago streets

22nd Avenue west side from Taraval to Santiago streets

29th Avenue west side from Taraval to Santiago streets