FINAL UPDATE: Delay near Ocean and Aptos has cleared. IB #KIngleside resuming service. (More: 14 in last 48 hours)

This page has older content

Please see Related Projects on this page for current project information. We are keeping this page as a record of SFMTA outreach.

L Taraval Improvement Forecast and Project Segment B Update – January 28 – February 8, 2023

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit
Walking
Route(s) Affected

We have weathered the storm at the onset of the new year. Although extreme weather conditions delayed some construction activities on the L Taraval Improvement Project, adjustments have been made and crews are back on schedule. In the coming weeks, work continues on water and sewer lines, as well as on the overhead contact system (OCS) that powers the trains. OCS work is now focused on foundation work to prepare for the installation of new poles. Construction teams will be excavating and jackhammering pavement, which may cause vibrations. Materials are also being temporarily staged nearby. Dust control and housekeeping measures are in place at active construction and staging locations.

The inbound bus stop at Taraval and 15th has been relocated across the intersection until fall 2024.

General construction hours are Monday to Friday between 8:00 a.m. and 4:00 p.m. Construction schedules are subject to change. “No Parking” signs will be posted in construction and staging areas, and intersections may be closed to through traffic on Taraval Street.

Multiple agencies are performing infrastructure work in the area. This includes work by Public Works on 19th Avenue, Public Utilities Commission at Vicente and Wawona streets and PG&E along Taraval Street.

L Taraval Improvement Project – Segment B

Construction work is scheduled to be performed - January 28 – February 8, 2023

Taraval Street

15th to 19th avenues: waterline work, excavate, measure and sewer laterals

16th to 18th avenues: OCS pole work

23rd to 23th avenues: sewer line work

24th to 26th avenues: OCS pole work

24th to 28th avenues: waterline work, excavate and shore, connection holes

28th to 30th avenues: OCS pole work

Sunset Boulevard to 36th Avenue: waterline work

Ulloa Street

14th Avenue to Funston Street: water line work, excavation and shoring, water service change over

Ulloa street and 14th Avenue: OCS pole work

Temporary staging locations

14th Avenue west side from Ulloa to Vicente streets

16th Avenue west side from Taraval to Ulloa streets

22nd Avenue west side from Taraval to Santiago streets

24th Avenue east side from Taraval to Santiago streets

26th Avenue east side from Tarava to Santiago streets

27th Avenue west side from Taraval to Ulloa streets

28th Avenue east side from Taraval to Ulloa streets

29th Avenue west side from Taraval to Santiago streets

33rd Avenue east side from Taraval to Santiago streets

Weekend PG&E work performed on Taraval Street, unrelated to the L Taraval Improvement Project.

Work conducted by PG&E is scheduled for the following times:

  • January 28, 2023 between 9:00 a.m. to 3:00 p.m.
    19th and 20th avenues on Taraval Street at the southwest corner to perform gas main replacement. Parking will be briefly impacted with no lane closures.  
  • February 4 – 5, 2023 between 8:00 a.m. and 4:00 p.m.
    30th to 31st avenues on Taraval Street on the north and south sides to perform gas service relocation. Parking will be briefly impacted with no lane closures.