L Taraval Improvement Project Work Forecast Aug. 26-Sept.6

Monday, August 26, 2019 - 7:00am
Neighborhoods Affected
Route(s) Affected

Work planned August 26 to September 6, 2019

No work on Labor Day: September 2, 2019

Details of Work Performed:
  • Excavation of small exploratory holes to verify the locations of existing underground utilities is planned for August 26-30
  • Sewer main replacement is planned for August 26-30 and September 3-6
  • Two large manholes will be constructed as part of the sewer mainline work
What to Expect: Excavation requires jackhammering of the pavement. Dust control measures will be in place to prevent dust kick up from the work.
Location and Time of Work:
  • Northside of Taraval Street between 46th and 45th Avenue
  • Monday to Friday, 7:00a.m. to 5:00p.m.
  • No work on Labor Day: September 2, 2019
Traffic Impacts: Some parking will be temporarily restricted in construction zones and traffic lanes will be modified in the northbound lane during active work. 
   

The following two-week construction forecast is subject to change due to weather delays or unexpected field conditions.

Questions or concerns? Contact us at Jerri.Diep@SFMTA.com or 415.646.2382