America's Cup 34 People Plan

Project Overview

America's Cup Wayfinding Signage

The People Plan is a transportation implementation plan developed to support the 34th America's Cup (AC34) and associated sailing regattas during both the 2012 and 2013 events (“the Events”). The City and County of San Francisco is developing a series of Implementation Plans in close coordination with the America's Cup Event Authority and the America's Cup Race Management, along with appropriate federal, state, regional, and local agencies, as well as interested organizations and individuals.

Upcoming meetings

No upcoming meetings have been posted

Latest updates

Project Details

The People Plan is a transportation implementation plan developed to support the 34th America's Cup (AC34) and associated sailing regattas during both the 2012 and 2013 events (“the Events”). The City and County of San Francisco is developing a series of Implementation Plans in close coordination with the America's Cup Event Authority and the America's Cup Race Management, along with appropriate federal, state, regional, and local agencies, as well as interested organizations and individuals.

The People Plan was developed with extensive public input. Three progress reports document stakeholder input and responses as the People Plan progressed:
 
 
 

PROJECT HIGHLIGHTS:

  • Providing a mobility plan for the Waterfront Area of San Francisco during the America’s Cup events of 2012 and 2013.
  • Integrating existing modes into a coherent, regional transportation system that is easily accessed and understood by all.
  • Educating the public on the benefits of collective and non-motorized transportation during America’s Cup and beyond.
  • Providing clear incentives for visitors, organizers and local residents to use alternative modes of transportation to the private car

 

TIMELINE:

Key Dates/Deadlines

Milestones

Winter 2010

Presentation of project to numerous local and regional stakeholders

April 2011

Submittal of initial People Plan and Progress Report to the AC34 Authority

September 2011

Submittal of final draft of People Plan to AC34 Authority

December 2011

Certification of the AC34 EIR by the Board of Supervisors

August 2012

Initial implementation of the People Plan for 2012 races

June 2013

Revised final People Plan for AC34

July -September 2013

Implementation of the People Plan for AC34

 

FUNDING:

Work related to the America’s Cup People Plan is slated to be partly funded by the America’s Cup Organizing Committee, based on cost estimates submitted by the City and its regional partners as part of the People Plan.  Additional funding will likely come from local and regional sources and revenues generated by the Events themselves.

 

OUR PARTNERS:

The SFMTA has worked closely with the Office of Economic and Workforce Development (OEWD), which serves as the lead agency representing the City for AC34, and with the Port of San Francisco and the San Francisco Planning Department.  As the principal author of the People Plan, the SFMTA also coordinated input and content from all major regional transportation providers, including BART, Caltrans, MTC, Caltrain, Golden Gate Transit, AC Transit, WETA and the SFCTA.  

The SFMTA is also working closely with 511 and the America’s Cup Event Authority on communicating transportation choices for the events. 

Documents

AttachmentSize
PDF Progress Report #1111.63 KB
PDF Progress Report #22.65 MB
PDF Progress Report #32.02 MB
PDF Final People Plan4.38 MB