511: Van Ness Construction Forecast: August 21-September 1, 2017 5 days ago More...

The following Van Ness Improvement Project construction forecast is subject to change due to weather or unforeseen conditions. For more project details, please visit sfmta.com/vanness.

Work is planned over the next month to create two construction zones: one southbound on Van Ness Avenue from Sutter to McAllister streets, and another northbound from Jackson to Lombard streets. These work areas will be approximately five feet from the building line to approximately the center of the roadway.

To make space for these construction zones, the following changes will occur:

  • Blue curb parking for people with disabilities and loading zones will be temporarily relocated beginning Tuesday, August 22 (see map for locations)
  • Bus stop located on southbound Van Ness at McAllister will be reconfigured beginning Wednesday, August 23
  • Southbound traffic lanes are expected to shift Monday, August 28
  • Parking is expected to be temporarily removed for construction southbound Van Ness between Sutter and McAllister beginning Monday, August 28
  • Northbound traffic lanes are expected to shift Tuesday, September 5
  • Parking is expected to be temporarily removed for construction on northbound Van Ness between Jackson and Lombard beginning Tuesday, September 5

Project staff is reaching out directly to businesses and residents on blocks that are impacted by these changes. See the full schedule of expected activities below.

Those who travel in and through the area are advised to take alternate routes and plan for delays.

Monday, August 21: Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission Streets. Trenching and installation of duct banks for powering buses will continue between Grove to McAllister streets.

Between the hours of 10:00 p.m. and 6:00 a.m. existing lane striping will be removed and new lanes will be marked between Grove and Pine streets and between Washington and Lombard streets. Note: Neighbors are advised to anticipate construction-related noise as crews work diligently to complete this necessary night work.

Tuesday, August 22: Blue curb parking for people with disabilities and loading zones will begin being temporarily relocated between Sutter and McAllister (see map for locations). Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission Streets. Trenching and installation of duct banks for powering buses will continue between Grove to McAllister streets.

Between the hours of 10:00 p.m. and 6:00 a.m. existing lane striping will be removed and new lanes will be marked between Grove and Pine streets and between Washington and Lombard streets. Note: Neighbors are advised to anticipate construction-related noise as crews work diligently to complete this necessary night work.

Wednesday, August 23, through Friday, August 25: The transit stop for southbound buses on Van Ness Avenue at McAllister Street will be temporarily be shifted from the southwest corner to the northwest corner. The stop will return near to the southwest corner on Wednesday, August 30. Blue curb parking for people with disabilities and loading zones continue being temporarily relocated between Sutter and McAllister (see map for locations). Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission Streets. Trenching and installation of duct banks for powering buses will continue between Grove to McAllister streets.

Between the hours of 10:00 p.m. and 6:00 a.m. existing lane striping will be removed and new lanes will be marked between Grove and Pine streets and between Washington and Lombard streets. Note: Neighbors are advised to anticipate construction-related noise as crews work diligently to complete this necessary night work.

Monday, August 28: Southbound traffic lanes are expected to shift toward the center of the roadway to create a construction work zone on the southbound side of Van Ness Avenue from McAllister to Sutter streets. The transit stop for southbound buses on Van Ness Avenue at McAllister Street will be temporarily be shifted from the southwest corner to the northwest corner. The stop will return near to the southwest corner on Wednesday, August 30. Blue curb parking for people with disabilities and loading zones continue being temporarily relocated between Sutter and McAllister (see map for locations). Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission Streets. Trenching and installation of duct banks for powering buses will continue between Grove to McAllister streets.

Between the hours of 10:00 p.m. and 6:00 a.m. existing lane striping will be removed and new lanes will be marked between Grove and Pine streets and between Washington and Lombard streets. Note: Neighbors are advised to anticipate construction-related noise as crews work diligently to complete this necessary night work.

Tuesday, August 29: The transit stop for southbound buses on Van Ness Avenue at McAllister Street will be temporarily be shifted from the southwest corner to the northwest corner. The stop will return near to the southwest corner on Wednesday, August 30. Blue curb parking for people with disabilities and loading zones begin being temporarily relocated between Jackson and Lombard (see map for locations). Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission Streets. Trenching and installation of duct banks for powering buses will continue between Grove to McAllister streets.

Between the hours of 10:00 p.m. and 6:00 a.m. existing lane striping will be removed and new lanes will be marked between Sutter and Pine streets and between Washington and Lombard streets. Note: Neighbors are advised to anticipate construction-related noise as crews work diligently to complete this necessary night work.

Wednesday, August 30: The transit stop for southbound buses on Van Ness Avenue at McAllister Street will return near to its original location on the southwest corner. Blue curb parking for people with disabilities and loading zones continue being temporarily relocated between Jackson and Lombard (see map for locations). Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission Streets. Trenching and installation of duct banks for powering buses will continue between Grove to McAllister streets.

Between the hours of 10:00 p.m. and 6:00 a.m. existing lane striping will be removed and new lanes will be marked between Sutter and Pine streets and between Washington and Lombard streets. Note: Neighbors are advised to anticipate construction-related noise as crews work diligently to complete this necessary night work.

Thursday, August 31, through Friday, September 1: Blue curb parking for people with disabilities and loading zones continue being temporarily relocated between Jackson and Lombard (see map for locations). Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission Streets.

Between the hours of 10:00 p.m. and 6:00 a.m. existing lane striping will be removed and new lanes will be marked between Sutter and Pine streets and between Washington and Lombard streets. Note: Neighbors are advised to anticipate construction-related noise as crews work diligently to complete this necessary night work.


511: Van Ness Construction Forecast: August 14- August 25, 2017 2 weeks ago More...

The following Van Ness Improvement Project construction forecast is subject to change due to weather or unforeseen conditions. For more project details, please visit sfmta.com/vanness.

Work is planned over the next month to develop work zones for the upcoming utility work. This work will create two construction zones: one southbound on Van Ness Avenue from Sutter to McAllister streets, and another northbound from Jackson to Lombard streets. These work areas will be approximately five feet from the building line to approximately the center of the roadway.

To make space for these construction zones, traffic lanes will shift in late, parking will be temporarily removed, blue curb parking for people with disabilities and loading zones will be temporarily relocated, sidewalk widths will be reduced and bus stops will be reconfigured. Project staff is reaching out directly to businesses and residents on blocks that are impacted by these changes.

Those who travel in and through the area are advised to take alternate routes and plan for delays.

Monday, August 14, through Friday, August 18: Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission Streets. Existing lane striping will be removed in the median between Grove and Bush streets and between Washington and Lombard streets. Trenching and installation of duct banks for powering buses will be done between Grove to McAllister streets.

Between the hours of 10:00 p.m. and 6:00 a.m. existing lane striping will be removed and new lanes will be marked between Grove and Bush streets and between Washington and Lombard streets. Note: Neighbors are advised to anticipate construction-related noise as crews work diligently to complete this necessary night work.

Monday, August 21, through Friday, August 25: Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission Streets. Trenching and installation of duct banks for powering buses will be done between Grove to McAllister streets.


76X-Marin Headlands Express


Live map © 2017 NextBus Inc.
View 76X-Marin Headlands Express in a larger map

This route runs on Saturdays, Sundays, and the following holidays: New Year’s Day, Presidents Day, Dr. Martin Luther King Jr. Day, Memorial Day, July 4, Labor Day, Thanksgiving and Christmas Day.

Field Road is served on the Outbound trip only.

Inbound

Mitchell, Bunker, McCullough, Conzelman, Highway 101 (Golden Gate Bridge), Doyle Drive, Richardson, Lombard, Van Ness, Post, Kearny, Bush, Sansome, Sutter.

Inbound (express area)

Richardson and Francisco to Sansome and Sutter. Stops: Richardson and Francisco; Lombard at Fillmore; Van Ness at Union, after Jackson, at Sacramento; Post after Van Ness, after Jones, after Powell, between Stockon and Grant; Kearny at Bush; Bush after Montgomery; Sansome at Sutter.

Outbound

From Sansome and Sutter via Sutter, Van Ness, Lombard, Richardson, Doyle Drive, Highway 101 (Golden Gate Bridge), Alexander exit, Conzelman, McCullough, Bunker, Field, Alexander parking lot, Field, Bunker, Mitchell, Grassburn, Kirkpatrick, 1st to Fort Cronkhite parking lot.

Outbound (express area)

Richardson and Francisco to Sansome and Sutter. Stops: Sutter after Sansome, after Kearny, after Stockton, after Powell, after Leavenworth, at Van Ness; Van Ness after Clay, after Jackson, at Union; Lombard at Fillmore; Richardson at Francisco.

Related current projects

Related past projects