Cable Car Maintenance Work: February 18 to September 10, 2025

Share this:
Service Affected
Accessibility
Transit
Neighborhoods Affected

Event Summary

As part of ongoing maintenance of the cable cars and their infrastructure, from Tuesday, February 18, and running until Wednesday, Septemeber 10, 2025, cable car maintenance will refurbish and reinstall all 21 sheaves (grooved wheels) that guide the underground cables and allow the cable cars to travel along their routes.

For complete project details, please visit the Cable Car Sheaves Upgrade Project webpage.

Muni Service Changes

The cable car lines will be broken up into the following four segments:

  • California segment
  • Hyde segment
  • Mason segment
  • Powell segment

When a segment is being worked on bus shuttles will provide service along that segment. At least one cable car line will remain open to the public during normal operating hours while sections are being upgraded.

Please refer to the table below for information on which segments will be work on which dates.

Notes:

  • All work is subject to weather and other conditions.
  • Be sure to receive real-time Muni service alerts via email or text by signing up through our Email and Text Subscriptions page.
Day Date Work Location Segments to Be Motorized
Tuesday 5/13/25 California out - Barn California and Hyde
Tuesday 5/20/25 Hyde in - Barn California and Hyde
Tuesday 6/3/25 Powell and Market Powell
Tuesday 6/10/25 Hyde-Powell turnaround Hyde
Tuesday 7/15/25 Bay and Taylor Mason
Tuesday 7/22/25 Pacific and Hyde California and Hyde
Tuesday 7/29/25 California and Hyde California
Tuesday 8/5/25 Beach and Hyde Hyde
Tuesday 8/26/25 Powell and Washington Powell, Mason and Hyde
Wednesday 8/27/25 Powell and Washington Powell, Mason and Hyde
Tuesday 9/9/25 California and Mason California
Wednesday 9/10/25 California and Mason California