Vision Zero Signal Retiming

Project Updates (8/12/2024)

  • Dolores and Guerrero Street locations completed 4/22/2023
  • Valencia Street locations completed 6/21/2023
  • Folsom Street locations completed 7/10/2023
  • Geary Blvd. Park Presidio Blvd, and 25th Ave. locations completed 10/2/2023
  • Various individual locations completed 1/15/2024
  • Fell and Oak Street locations completed 4/7/2024
Share this:
Project Timeline
Design
Spring 2022 - Spring 2023
Completed
Implementation
Spring 2023 - Fall 2024
Pending
Статус проекта (Project Status)
  1. Implementation / Construction
Усовершенствования (Improvements)