L Taraval Improvement Project Work Forecast May 31 to June 11, 2021

Service Affected
Driving
Transit
Neighborhoods Affected
Details of Work Performed:
  • Staging area demobilized to fully open Lower Great Highway: To minimize the inconvenience for the neighbors and drivers, we are starting to shrink the footprint of the staging area on Lower Great Highway. Following the opening of the block between Santiago and Taraval streets in May, we will clean up and demobilize the next block between Taraval and Ulloa streets. On Friday, June 11, the northbound lane of Lower Great Highway will be fully open to vehicular traffic. The SFMTA would like to thank the community for the support during the lane closure while we were making improvements to Taraval Street.
     
  • L Bus serves regular stops: As we are wrapping up the streetscape and landscaping work on Taraval Street, the L bus is now serving the regular stops between Embarcadero and the SF Zoo. Since Saturday, May 15, all subway stations have reopened for the N Judah and KT Ingleside Third train service. The L customers now have an option of transferring between L bus and KT train at West Portal station. As the L bus is not serving Forest Hill Station anymore, customers can transfer to 44 O’Shaughnessy to access that station.
     
  • Streetscape and landscape work is ongoing with minimum impact until later this summer on Taraval*:
     
  • Cleaning up and reorganizing the staging area is planned for:
    • June 1-10 on Lower Great Highway between Ulloa and Taraval streets
       
  • Running drainage tests and planting trees are planned for:
    • June 1-4 between Sunset Blvd. and 46th Ave. on both sides of the street
       
  • Planting shrubs and installing mulches are planned for:
    •  June 1-11 in the island planters between 37th and 46th avenues
       
  • Sealing the gap in the back of curbs and sidewalks is planned for:
    • June 7-11 between Sunset Boulevard and 46th Avenue on both sides of the street

*In observance of Memorial Day, the contractor will not work on Monday, June 31, 2021.

What to Expect:

Noise and dust control measures will be in place to prevent disturbances from the work.

Time of Work:

Monday to Friday 8:00 a.m to 5:00 p.m.; Saturday to Sunday 8:00 a.m to 5:00 p.m. Hours subject to change based on construction needs. 

Traffic Impacts:

Some parking will be temporarily restricted in construction zones and traffic lanes will be modified during active work.



The above construction forecast is subject to change due to weather delays or unexpected field conditions.

Questions or concerns? Contact us at LTaravalProject@SFMTA.com or 415.701.4387

Stay Up To Date: For L Taraval Improvement Project work forecast and updates, please sign-up for email updates by visiting SFMTA.com/LTaravalProject.

☎ 311 (Outside SF 415.701.2311; TTY 415.701.2323) Free language assistance / 免費語言協助 / Ayuda gratis con el idioma / Бесплатная помощь переводчиков / Trợ giúp Thông dịch Miễn phí / Assistance linguistique gratuite / 無料の言語支援 / 무료 언어 지원 / Libreng tulong para sa wikang Filipino / การช่วยเหลือทางด้านภาษาโดยไม่เสียค่าใช้จ่าย / خط المساعدة المجاني على الرقم