May 25-June 3, 2013 During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. No Central Subway construction is planned in Chinatown or North Beach. For...
Construction Update Dec. 29, 2012- Jan. 7, 2013 During the next 10 days, construction to prepare for tunneling will continue in SoMa and recommence in Union Square. No Central Subway construction is...
August 17-26, 2013 During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. In North Beach, demolition of the Pagoda Palace will continue. No Central...
Construction Update Jan. 19-28, 2013 During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. In North Beach, AT&T will perform work to complete the...
Central Subway Project Advancements January 17 - January 26, 2015 This section contains brief updates about recent construction activities and a look-ahead for what to expect in Southern SoMa,...
Construction Update March 23-April 1, 2013 During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. No Central Subway construction is planned to occur in...
Project Advancements December 20, 2014 - January 2, 2015 During the next 14 days, Central Subway work continues at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief...
Construction Update Feb. 16-25, 2013 During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. No Central Subway construction is planned to occur in...
Construction Update March 30-April 8, 2013 During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. No Central Subway construction is planned to occur in...
Central Subway Project Advancements January 31 - February 9, 2015 This section contains brief updates about recent construction activities and a look-ahead for what to expect in Southern SoMa,...
Construction Update Jan. 12-21, 2013 During the next week, construction to prepare for tunneling will continue in SoMa and Union Square. In North Beach, AT&T will be performing work to complete...
Construction Update Jan. 26-Feb. 4, 2013 During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. No Central Subway construction is planned to occur in...
Construction Update March 16-25, 2013 During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. No Central Subway construction is planned to occur in...
Central Subway Project Advancements January 24 - February 2, 2015 This section contains brief updates about recent construction activities and a look-ahead for what to expect in Southern SoMa,...
Construction Update Feb. 23-March 4, 2013 During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. No Central Subway construction is planned to occur in...
Construction Update April 13-22, 2013 During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. No Central Subway construction is planned to occur in...
Central Subway Project Advancements February 21 - March 2, 2015 This section contains brief updates about recent construction activities and a look-ahead for what to expect in Southern SoMa, Northern...
Central Subway Project Advancements May 23 - June 1, 2015 This section contains brief updates about recent construction activities and a look-ahead for what to expect in Southern SoMa, Northern SoMa...
Central Subway Project Advancements May 30 - June 8, 2015 This section contains brief updates about recent construction activities and a look-ahead for what to expect in Southern SoMa, Northern SoMa...
Central Subway Project Advancements May 16 - May 25, 2015 This section contains brief updates about recent construction activities and a look-ahead for what to expect in Southern SoMa, Northern SoMa...
Project Advancements October 18 - October 27, 2014 During the next 10 days, Central Subway work continues at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief...
Project Advancements August 16 - August 25, 2014 During the next 10 days, Central Subway work continues at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief updates...
Project Advancements August 30 - September 8, 2014 During the next 10 days, Central Subway work continues at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief...
Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line...
Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line...