Van Ness Avenue Construction Forecast: September 17 - September 28, 2018

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit SFMTA.com/VanNess.

The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.

Tentative Schedule:

Lombard to Greenwich: Monday through Friday, September 24 through September 28, crews are scheduled to work on sidewalk replacement.

Greenwich to Filbert: Monday through Friday, September 24 through September 28, crews are scheduled to work on sidewalk replacement.

Filbert to Union: Monday through Friday, September 24 through September 28, crews are scheduled to work on sidewalk replacement.

Union to Green: Monday through Friday, September 24 through September 28, crews are scheduled to work on sidewalk replacement.

Vallejo to Broadway: Monday through Friday, September 17 through September 21, and Monday through Friday, September 24 through September 28, crews are scheduled to work on sidewalk replacement.

Broadway to Pacific: Monday through Friday, September 17 through September 21, and Monday through Friday, September 24 through September 28, crews are scheduled to work on sidewalk replacement.

Pacific to Jackson: Monday through Friday, September 17 through September 21, and Monday through Friday, September 24 through September 28, crews are scheduled to work on sidewalk replacement.

Jackson to Washington: Monday through Friday, September 17 through September 21, and Monday, September 24, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Monday through Friday, September 17 through September 21, crews are also scheduled to pothole for upcoming work.

Washington to Clay: Monday through Friday, September 17 through September 21, crews are scheduled to pothole for upcoming work. Friday, September 21, crews are also scheduled to prepare the area for upcoming sewer work.

Clay to Sacramento: Monday through Friday, September 17 through September 21, crews are scheduled to pothole for upcoming work. Friday, September 21, crews are also scheduled to prepare the area for upcoming sewer work.

Sacramento to California: Monday through Friday, September 17 through September 21, crews are scheduled to pothole for upcoming work. Monday through Friday, September 24 through September 28, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

California to Pine: Monday through Friday, September 17 through September 21, crews are scheduled to pothole for upcoming work. Monday through Friday, September 24 through September 28, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Pine to Bush: Monday through Friday, September 17 through September 21, crews are scheduled to pothole for upcoming work. Wednesday through Friday, September 19 through September 21, and Monday through Friday, September 24 through September 28, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Bush to Sutter: Monday through Friday, September 17 through September 21, and Monday through Friday, September 24 through September 28, crews are scheduled to work on sewer main installation and to pothole for upcoming work. Intensive noise and vibration is expected. Crews are also scheduled to install a joint-utility trench and perform water work.

Sutter to Post: Monday through Friday, September 17 through September 21, and Monday through Friday, September 24 through September 28, crews are scheduled to work on sewer main installation and installing a joint-utility trench. Intensive noise and vibration is expected. Tuesday, September 18, crews are also scheduled to perform water work. Monday through Friday, September 24, through September 28, crews are also scheduled to work on sidewalk replacement.

Post to Geary: Wednesday, September 19 and Thursday, September 20, crews are scheduled to work on water main installation.

Night work is scheduled Wednesday through Friday, September 19 through September 21, and Monday through Friday, September 24 through September 28, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on updating the emergency firefighting system. Disruptive noise is expected.

Geary to O'Farrell: Monday through Thursday, September 17 through September 20, crews are scheduled to work on water main installation. Monday through Friday, September 24 through September 28, crews are scheduled to pothole for upcoming work and to work on sidewalk replacement.

Night work is scheduled Monday through Friday, September 17 through September 21, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on updating the emergency firefighting system. Disruptive noise is expected and access to Myrtle street from the west side of Van Ness Avenue might be limited.

O'Farrell to Ellis: Monday through Friday, September 17 through September 21, and Monday through Friday, September 24 through September 28, crews are scheduled to work on sidewalk replacement. Monday, September 17 and Tuesday, September 18, crews are also scheduled to work on water main installation.

Ellis to Eddy: Monday through Wednesday, September 17 through September 19, crews are scheduled to work on sewer and water main installation.

Night work is scheduled Monday, September 17 and Tuesday, September 18, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on water main installation.

Eddy to Turk: Monday through Friday, September 17 through September 21, and Monday through Friday, September 24 through September 28, crews are scheduled to work on sidewalk replacement. Monday through Wednesday, September 17 through September 19, crews are also scheduled to work on sewer and water main installation.

Night work is scheduled Monday, September 17, and Tuesday, September 18, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on water main installation.

Golden Gate to McAllister: Monday through Friday, September 17 through September 21, crews are scheduled to work on sidewalk replacement.

McAllister to Grove: Monday through Friday, September 17 through September 21, and Monday through Friday, September 24 through September 28, crews are scheduled to work on sewer and water main installation. Intensive noise and vibration is expected.

Night work is scheduled Monday through Friday, September 17 through September 21, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on water main installation. Disruptive noise is expected.

Grove to Hayes: Monday through Friday, September 17 through September 21, and Monday through Friday, September 24 through September 28, crews are scheduled to work on sewer and water main installation. Intensive noise and vibration is expected. Tuesday through Friday, September 25 through September 28, crews are also scheduled to install a joint-utility trench.

Night work is scheduled Monday through Friday, September 17 through September 21, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on water main installation. Disruptive noise is expected.

Hayes to Fell: Monday through Friday, September 17 through September 21, and Monday through Friday, September 24 through September 28, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Fell to Market: Monday through Friday, September 17 through September 21, and Monday through Friday, September 24 through September 28, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Night work is scheduled Monday through Friday, September 24 through September 28, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.