Van Ness Avenue Construction Forecast: November 12 - November 21, 2018

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit
Walking

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit SFMTA.com/VanNess.

The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.

Tentative schedule:

In the next two weeks crews are scheduled to work on sewer and water main installation, sidewalk replacement, installing a joint utility trench, street light conduits, potholing for upcoming work and updating the emergency firefighting water system.

Monday through Friday, November 12 through November 16

  • Chestnut to Lombard Night work is also scheduled Wednesday and Thursday, between the hours of 8:00 p.m. and 7:00 a.m. Disruptive noise is expected.
  • Lombard to Greenwich: Night work is scheduled Wednesday and Thursday, between the hours of 8:00 p.m. and 7:00 a.m. Disruptive noise is expected.
  • Filbert to Union
  • Vallejo to Broadway
  • Pacific to Jackson
  • Jackson to Washington (Monday and Tuesday only) *Intensive noise and vibration expected
  • Washington to Clay (Wednesday to Friday only) *Intensive noise and vibration expected. Night work is also scheduled Friday, November 16, between the hours of 8:00 p.m. and 7:00 a.m. Intensive noise is expected.
  • Clay to Sacramento: Night work is scheduled Tuesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. Intensive noise and vibration is expected.
  • Sacramento to California: Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. Intensive noise and vibration is expected.
  • California to Pine: Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. Intensive noise and vibration is expected.
  • Pine to Bush: Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. Intensive noise and vibration is expected.
  • Bush to Sutter: Night work is scheduled Friday, November 16, between the hours of 8:00 p.m. and 7:00 a.m. Intensive noise is expected.
  • Sutter to Post
  • Post to Geary
  • Geary to O'Farrell
  • Ellis to Eddy: Night work is scheduled Wednesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Eddy to Turk: Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Turk to Golden Gate: Night work is scheduled Monday through Wednesday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Grove to Hayes
  • Fell to Market (Wednesday through Friday only) Night work is also scheduled Monday and Tuesday, between the hours of 8:00 p.m. and 7:00 a.m. Disruptive noise is expected.
  • Market to Mission

Sunday, November 18 through Tuesday November 20, Night work is scheduled between the hours of 8:00 p.m. and 7:00 a.m.

  • Clay to Sacramento *Intensive noise and vibration is expected.
  • Sacramento to California *Intensive noise and vibration is expected.
  • California to Pine *Intensive noise and vibration is expected.
  • Pine to Bush: *Intensive noise and vibration is expected.
  • Bush to Sutter
  • Ellis to Eddy
  • Eddy to Turk

Monday through Wednesday, November 19, through November 21

  • Bay to Francisco
  • Filbert to Union
  • Union to Green
  • Washington to Clay *Intensive noise and vibration is expected.
  • Sutter to Post
  • Post to Geary
  • Geary to O'Farrell
  • Grove to Hayes
  • Fell to Market
  • Market to Mission