Van Ness Avenue Construction Forecast: March 25 - April 6, 2018

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit sfmta.com/vanness.

The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.

Tentative Schedule:

Greenwich to Filbert: Monday, March 26, through Friday, March 30, crews are scheduled to work on sewer main installation. Monday, April 2, through Friday, April 6, crews are schedule to work on sewer main installation at the intersection of Filbert. Due to sewer main installation work, intensive noise and vibration is expected.

Sewer main installation is scheduled to occur at the intersection of Greenwich on Monday, March 26 and Tuesday, March 27, between the hours of 8:00 p.m. and 7:00 a.m. Intensive noise and vibration is expected during this time.

Green to Vallejo: Monday, March 26, through Wednesday, March 28, crews are scheduled to work on sewer main installation at the intersection of Green. Monday, April 2, through Friday, April 6, crews are scheduled to work on sewer main installation and are also scheduled to pothole for upcoming work. Due to sewer main installation work, intensive noise and vibrations are expected.

Night work is scheduled Monday, March 26, between the hours of 8:00p.m. and 7:00a.m., when crews are scheduled to pothole at the intersection of Vallejo to confirm underground utilities for upcoming sewer work.

Jackson to Washington: Night work is scheduled Sunday, March 25, through Thursday, March 29, between the hours of 8:00 p.m. and 7:00 a.m., when crews are expected to work on the emergency firefighting water system.

Washington to Clay: Night work is scheduled Sunday, March 25, through Friday, March 29, between the hours of 8:00 p.m. and 7:00 a.m., when crews are expected to work on the emergency firefighting water system.

Clay to Sacramento: Night work is scheduled Sunday, April 1, through Tuesday, April 3, between the hours of 8:00 p.m. and 7:00 a.m., when crews are expected to work on the emergency firefighting water system.

Sacramento to California: Night work is scheduled Wednesday, April 4, through Thursday, April 5, between the hours of 8:00 p.m. and 7:00 a.m., when crews are expected to work on the emergency firefighting water system.

Sutter to Post: Monday through Friday, March 26 through Marcy 30 and April 2 through April 6, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Geary to O'Farrell: Monday, March 26, through Friday, March 30, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Ellis to Eddy: Wednesday, April 4, through Friday, April 6, crews are scheduled to work on sewer main installation at the intersection of Ellis. Intense noise and vibration is expected.

Night work is scheduled Monday through Friday, March 26 through 30 and April 2 through April 6, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on water main installation at the intersection of Eddy.

Turk to Golden Gate: Monday, March 26, sewer-related work is scheduled at the intersection of Golden Gate. Monday, March 26, through Friday, March 30, crews are scheduled to work on a joint utility trench at the intersection of Golden Gate. Monday, March 26, through Friday, March 30, and Monday, April 2, through Tuesday, April 3, crews are scheduled to work on sewer main installation at the intersection of Turk. Intensive noise and vibration is expected. Monday, April 2, through Friday, April 6, crews are scheduled to work on a joint utility trench at the intersection of Turk. Monday, April 2, through Friday, April 6, crews are also scheduled to pothole for upcoming work.

Golden Gate to McAllister: Monday, March 26, sewer-related work is scheduled at the intersection of Golden Gate. Monday, March 26, through Friday, March 30, crews are scheduled to work on a joint utility trench at the intersection of Golden Gate. Monday, March 26, through Friday, March 30, crews are scheduled to pothole for upcoming work. Monday, March 26, through Thursday, March 29, sewer-related work is scheduled to occur at the intersection of McAllister.

Night work is scheduled Monday, March 26, and Tuesday, March 27, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on water main installation at the intersection of McAllister.

Fell to Market: Night work is scheduled Wednesday, March 28, through Friday, March 30, and Monday, April 2, through Friday, April 6, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm utilities for upcoming sewer work.