Van Ness Construction Forecast: May 21 - June 1, 2018

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit sfmta.com/vanness.

The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.

Tentative Schedule:

Chestnut to Lombard: Monday, May 21, through Friday, May 25, crews are scheduled to work on water main installation.Tuesday, May 29, through Friday, June 1, crews are scheduled to pothole for upcoming work.

Night work is scheduled Monday, May 21, through Friday, May 25, and Tuesday, May 29, through Friday, June 1, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation. Disruptive noise is expected.

Lombard to Greenwich: Monday, May 21, through Friday, May 25, crews are scheduled to work on water main installation. Wednesday, May 23, through Friday, May 25, crews are also scheduled to pothole for upcoming work.

Night work is scheduled Monday, May 21, through Friday, May 25, and Tuesday, May 29, through Friday, June 1, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer and water main installation. Disruptive noise is expected.

Greenwich to Filbert: Monday, May 21, through Friday, May 25, and Tuesday, May 29, through Friday, June 1, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Monday, May 21, through Wednesday, May 23, crews are also scheduled to pothole for upcoming work.

Night work is scheduled Monday, May 21, and Tuesday, May 22, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Night work is also scheduled Monday, May 21, through Friday, May 25, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on water main installation.

Filbert to Union: Monday, May 21, through Friday, May 25, and Tuesday, May 29, through Friday, June 1, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Monday, May 21, crews are also scheduled to pothole for upcoming work.

Night work is scheduled Monday, May 21, and Tuesday, May 22, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Night work is also scheduled Monday, May 21, through Friday, May 25, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on water main installation.

Green to Vallejo: Wednesday, May 23, through Friday, May 25, and Tuesday, May 29, through Friday, June 1, crews are scheduled to work on on roadway restoration.

Vallejo to Broadway: Tuesday, May 29, through Friday, June 1, crews are scheduled to work on water main installation.

Broadway to Pacific: Tuesday, May 22, through Friday, May 25, and Tuesday, May 29, through Friday, June 1, crews are scheduled to work on sewer and water main installation. Due to sewer installation work, intensive noise and vibration is expected.

Pacific to Jackson: Tuesday, May 22, through Friday, May 25, and Tuesday, May 29, through Friday, June 1, crews are scheduled to work on sewer and water main installation. Due to sewer installation work, intensive noise and vibration is expected.

Jackson to Washington: Tuesday, May 29, through Friday, June 1, crews are scheduled to work on water main installation.

Night work is scheduled Friday, June 1, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.

Washington to Clay: Night work is scheduled Wednesday, May 30, through Friday, June 1, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled prepare the area and to pothole to confirm underground utilities for upcoming sewer work.

Sutter: Thursday, May 31, and Friday, June 1, crews are scheduled to work on water main installation.

O'Farrell to Ellis: Monday, May 21, through Friday, May 25, and Tuesday, May 29, through Friday, June 1, crews are scheduled to work on sewer main and water main installation. Due to sewer installation work, intensive noise and vibration is expected.

Ellis to Eddy: Monday, May 21, through Friday, May 25, and Tuesday, May 29, through Friday, June 1, crews are scheduled to work on sewer main installation and on installing a joint-utility trench. Due to sewer installation work, intensive noise and vibration is expected.

Eddy to Turk: Monday, May 21, through Friday, May 25, and Tuesday May, 29, through Friday, June 1, crews are scheduled to work on sewer main installation. Due to sewer main installation, intensive noise and vibration is expected, and access to Larch Street from the west side of Van Ness Avenue will be closed temporarily. Monday, May 21, through Friday May 25, crews are also scheduled to install a joint-utility trench and to work on water main installation. Thursday, May 31, and Friday, June 1, crews are also scheduled to pothole for upcoming work.

Golden Gate to McAllister: Night work is scheduled Monday, May 21, through Friday, May 25, and Tuesday, May 29, through Friday, May 1, between the hours of 8:00 p.m. and 7:00 a.m., when crews are expected to work on updating the emergency firefighting water system. Disruptive noise is expected.

Grove to Hayes: Night work is scheduled Monday, May 21, through Friday, May 25, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.

Fell to Market: Night work is scheduled Tuesday, May 29, through Friday, June 1, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.

Market to Mission: Night work is scheduled Monday, May 21, through Friday, May 25, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.