Work Forecast Plan for the Weeks of March 9 to March 20, 2020 Details of Work Performed: Continuation of sewer main replacement is planned for the weeks of: March 9-13 and March 16-20 between 46th...
In the next two weeks crews are scheduled to work on sewer and water main installation, installing a joint-utility trench, sidewalk and roadway replacement and light pole installation. The work...
Thursday, March 12, 2020 to Friday, March 20, 2020
Those traveling on the corridor are advised to stay alert and allow more travel time during construction. Polk Street, one block east of Van Ness Avenue, is a recommended alternative for people...
Work Forecast Plan for the Weeks of March 23 to April 3, 2020 Details of Work Performed: Continuation of sewer main replacement is planned for the weeks of: March 26-27 and March 30-April 3 between...
Per the City and County of San Francisco's Public Health Order , essential infrastructure projects, including the Van Ness Improvement Project, continue. The work underway on Van Ness Avenue is...
Those traveling on the corridor are advised to stay alert and allow more travel time during construction. Polk Street, one block east of Van Ness Avenue, is a recommended alternative for people...
Thursday, February 27, 2020 to Monday, March 2, 2020
This page was last updated on Wednesday, February 26, 2020. Throughout February and into the beginning of March, a major motion picture will be filming scenes in various locations in the Financial...
Following the completion of the Church Station outbound platform elevator last October, the rehabilitation of the outbound street elevator at this station will start the first week of March 2020. The...
As part of the Geary Rapid Project , work to replace aging water and sewer lines on Geary Boulevard, in coordination with San Francisco Public Utilities Commission, continues. Water main replacement...
Those traveling on the corridor are advised to stay alert and allow more travel time during construction. Polk Street, one block east of Van Ness Avenue, is a recommended alternative for people...
The following two-week construction forecast is tentative and subject to change due to weather delays, unexpected field conditions or construction crew availability. Construction crews are scheduled...
As part of the Geary Rapid Project , work to replace aging water and sewer lines on Geary Boulevard, in coordination with San Francisco Public Utilities Commission, continues. Water main replacement...
Those traveling on the corridor are advised to stay alert and allow more travel time during construction. Polk Street, one block east of Van Ness Avenue, is a recommended alternative for people...
Starting Saturday, February 22, 2020, Muni is introducing major changes to improve service. On This Page New Weekend Early Morning Metro Bus Service 23 Monterey Reroute 7 Haight/Noriega Upgrades...
The following two-week construction forecast is tentative and subject to change due to weather delays, unexpected field conditions or construction crew availability. Construction crews are scheduled...
Update for users of the Townsend Corridor from the 3rd Street Transit and Safety Project Thank you to community members who provided feedback on proposed improvements at the January 24, 2020 SFMTA...
Work Forecast Plan for the Weeks of February 24 to March 6, 2020 Details of Work Performed: Continuation of sewer main replacement is planned for the weeks of: February 24-28 and March 2-6 betwene...
Electronic display boxes are being installed at the north end of Yerba Buena/Moscone Station's platform. This notice provides a general project update and look-ahead which includes information about...
Thanks for your interest in the 6th Street Pedestrian Safety Project. As we mentioned in our last update, the construction phase will begin no sooner than the end of 2020. We will make sure to...
As part of the Geary Rapid Project , work to replace aging water and sewer lines on Geary Boulevard, in coordination with San Francisco Public Utilities Commission, continues. Water main replacement...
Those traveling on the corridor are advised to stay alert and allow more travel time during construction. Polk Street, one block east of Van Ness Avenue, is a recommended alternative for people...
Thank you to all of the community members that attended last week’s Valencia Bikeway Improvements Project Open House and Public Hearing. Overall, we had over 400 people drop-in at the event as well...
Thank you to all who joined us at last night’s meeting! We had a great turn-out and appreciate the thoughtful feedback provided. Three more opportunities to hear a project update are upcoming:...
Throughout most of 2017, the project team worked collaboratively with the Union Square Business Improvement District (BID), Powell Street hotels and businesses, other stakeholders, and the larger...