FINAL UPDATE: Delay near Market and Buchanan has cleared. OB #FMarket resuming service. (More: 23 in last 48 hours)

This page has older content

Please see Related Projects on this page for current project information. See Travel & Transit Updates for current travel updates. We are keeping this page as a record of SFMTA service and outreach.

Van Ness Avenue Construction Forecast: December 26, 2018 - January 4, 2019

Service Affected
Accessibility
Bicycle
Parking
Taxi
Driving
Transit
Walking

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit SFMTA.com/VanNess.

The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.

Tentative schedule:

In the next two weeks crews are scheduled to work on sewer and water main installation, sidewalk replacement, installing a joint utility trench and street light conduits, and potholing for upcoming work.

Wednesday through Friday, December 26 through December 28

  • Green to Vallejo Night work is scheduled Friday, December 28, between the hours of 8:00 p.m. and 7:00 a.m.
  • Vallejo to Broadway Night work is scheduled Wednesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Pacific to Jackson
  • Jackson to Washington
  • Washington to Clay
  • Clay to Sacramento
  • Sacramento to California
  • California to Pine
  • Pine to Bush
  • Sutter to Post Night work is scheduled Wednesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Post to Geary Night work is scheduled Wednesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • O'Farrell to Ellis
  • Ellis to Eddy
  • Grove to Hayes (Wednesday and Thursday only)
  • Hayes to Fell
  • Fell to Market (Friday only)

Wednesday through Friday, January 2 through January 4

  • Filbert to Union
  • Union to Green
  • Green to Vallejo Night work is scheduled Wednesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Vallejo to Broadway
  • Washington to Clay
  • Clay to Sacramento
  • Sacramento to California
  • California to Pine *Intensive noise and vibration is expected.
  • Geary to O'Farrell
  • Ellis to Eddy
  • Eddy to Turk
  • Turk to Golden Gate
  • Hayes to Fell
  • Fell to Market

*We are working on improving the format of our weekly construction forecasts. Please share your feedback with staff at VanNessBRT@SFMTA.com