Van Ness Avenue Construction Forecast: February 19 - March 1, 2019

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit
Walking

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit SFMTA.com/VanNess.

All night work is italicized below. The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.

Tentative schedule:

In the next two weeks crews are scheduled to work on sewer and water main installation, sidewalk replacement, installing a joint utility trench and street light conduits, and potholing for upcoming work.

Tuesday through Friday, February 19 through February 22

  • Chestnut to Lombard Night work is scheduled Tuesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Lombard to Greenwich. Night work is scheduled Tuesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Greenwich to Filbert. Night work is scheduled Tuesday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
  • Filbert to Union. Night work is also scheduled Tuesday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
  • Union to Green. Night work is also scheduled Tuesday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
  • Green to Vallejo.
  • Washington to Clay.
  • Clay to Sacramento.
  • Sacramento to California. *Intensive noise and vibration is expected on Friday, February 22.
  • California to Pine. (Friday only) *Intensive noise and vibration is expected on Friday, February 22.
  • Pine to Bush.
  • Bush to Sutter. (Tuesday through Thursday only) Intensive noise and vibration is expected.
  • Sutter to Post. (Tuesday through Thursday only) Intensive noise and vibration is expected.
  • Post to Geary.
  • Geary to O'Farrell.
  • Ellis to Eddy. (Thursday and Friday only)
  • Golden Gate to McAllister (Thursday and Friday only)
  • McAllister to Grove.
  • Grove to Hayes.
  • Hayes to Fell.
  • Fell to Market. Night work is scheduled Tuesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. *Intensive noise and vibration is expected.
  • Market to Mission.

Monday through Friday, February 25 through March 1

  • Lombard to Greenwich. (Wednesday through Friday only)
  • Greenwhich to Filbert. (Tuesday through Friday only)
  • Filbert to Union. (Monday and Tuesday only) Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Union to Green. (Monday and Tuesday only) Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Green to Vallejo. (Monday and Tuesday only)
  • Vallejo to Broadway.
  • Broadway to Pacific.
  • Pacific to Jackson.
  • Clay to Sacramento. Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Sacramento to California. *Intensive noise and vibration is expected. Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • California to Pine. *Intensive noise and vibration is expected.
  • Bush to Sutter. Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Sutter to Post. Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Post to Geary.
  • Geary to O'Farrell.
  • Ellis to Eddy.
  • Golden Gate to McAllister. Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • McAllister to Grove. (Tuesday through Thursday only.) Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Grove to Hayes.
  • Hayes to Fell. (Tuesday through Thursday only)
  • Fell to Market. (Tuesday through Friday only) Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. *Intensive noise and vibration is expected.
  • Market to Mission.

*We are working on improving the format of our weekly construction forecasts. Please share your feedback with staff at VanNessBRT@SFMTA.com