Van Ness Avenue Construction Forecast: February 19 - March 2, 2018

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit sfmta.com/vanness.

Tentative Schedule:

Monday, February 19: Between the hours of 8:00 p.m. and 7:00 a.m., sewer main is expected to be installed in intersections between McAllister and Eddy streets and between Vallejo and Chestnut streets. Neighbors are advised to anticipate intensive construction-related noise and vibrations, including saw cutting and pile driving, as crews work diligently to complete this necessary night work.

Tuesday, February 20, through Friday, February 23: Crews plan to be working on a joint trench to power overhead wires for buses from Turk to Ellis and from Geary to Post. Potholing is planned between Jackson and Lombard streets. Sewer main is expected to continue being installed in intersections between McAllister and Eddy streets and between Vallejo and Chestnut streets. Neighbors are advised to anticipate intensive construction-related noise and vibrations, including saw cutting and pile driving.

Between the hours of 8:00 p.m. and 7:00 a.m., sewer main is expected to be installed in intersections between McAllister and Eddy streets and between Vallejo and Chestnut streets. Neighbors are advised to anticipate intensive construction-related noise and vibrations, including saw cutting and pile driving, as crews work diligently to complete this necessary night work.

Sunday, February 25: Between the hours of 8:00 p.m. and 7:00 a.m., sewer main is expected to be installed in intersections between McAllister and Eddy streets and between Vallejo and Chestnut streets. Neighbors are advised to anticipate intensive construction-related noise and vibrations, including saw cutting and pile driving.

Monday, February 26, through Friday,  March 2: Crews plan to be working on a joint trench to power overhead wires for buses from Turk to Ellis and from Geary to Post. Potholing is planned between Jackson and Lombard streets. Sewer main is expected to continue being installed between McAllister and Geary streets and between Vallejo and Lombard streets. Neighbors are advised to anticipate intensive construction-related noise and vibrations, including saw cutting and pile driving.

Between the hours of 8:00 p.m. and 7:00 a.m., sewer main is expected to be installed in intersections between McAllister and Eddy streets and between Vallejo and Chestnut streets. Potholing to confirm locations of utilities is planned between O'Farrell and Sutter streets. Neighbors are advised to anticipate intensive construction-related noise and vibrations, including saw cutting and pile driving.

 

Basement Assessments

Before utility, roadway and sidewalk work begins, the Van Ness Improvement Project team is inspecting Van Ness Avenue basements that may extend below sidewalks. If your building has a sub-sidewalk basement, or if your building has a basement and you are not sure if it is a sub-sidewalk basement, please email vannessbrt@sfmta.com or 415.646.2317 to schedule a visit.