Van Ness Avenue Construction Forecast: January 2 - January 11, 2019

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit
Walking

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit SFMTA.com/VanNess.

The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.

Tentative schedule:

In the next two weeks crews are scheduled to work on sewer and water main installation, sidewalk replacement, installing a joint utility trench and street light conduits, and potholing for upcoming work.

Wednesday through Friday, January 2 through January 4

  • Filbert to Union
  • Union to Green
  • Green to Vallejo Night work is scheduled Thursday and Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Vallejo to Broadway Night work is also scheduled Wednesday, January 2, between the hours of 8:00 p.m. and 7:00 a.m.
  • Washington to Clay
  • Clay to Sacramento
  • Sacramento to California
  • California to Pine *Intensive noise and vibration is expected
  • Sutter to Post Night work is scheduled Wednesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Post to Geary Night work is scheduled Wednesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Ellis to Eddy
  • Eddy to Turk
  • Grove to Hayes
  • Hayes to Fell
  • Fell to Market

Monday through Friday, January 7 through January 11

  • Lombard to Greenwich Night work is scheduled Friday, January 11, between the hours of 8:00 p.m. and 7:00 a.m. Disruptive noise is expected.
  • Greenwich to Filbert Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Filbert to Union Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Union to Green Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Green to Vallejo Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Vallejo to Broadway (Monday and Tuesday only) Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Broadway to Pacific Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Washington to Clay *Intensive noise and vibrations is expected
  • Clay to Sacramento
  • Sacramento to California
  • California to Pine
  • Geary to O'Farrell. Note: Myrtle Street is scheduled to be closed for work Wednesday through Friday
  • O'Farrell to Ellis (Monday through Wednesday only)
  • Ellis to Eddy
  • Eddy to Turk
  • Turk to Golden Gate
  • McAllister to Grove (Tuesday through Friday only)
  • Grove to Hayes (Tuesday through Friday only)
  • Hayes to Fell
  • Fell to Market

*We are working on improving the format of our weekly construction forecasts. Please share your feedback with staff at VanNessBRT@SFMTA.com