Van Ness Avenue Construction Forecast: May 28 - June 7, 2019

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit
Walking

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit SFMTA.com/VanNess.

All night work is italicized below. The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.

Those traveling on the corridor are advised to stay alert and allow more travel time during construction. Polk Street, one block east of Van Ness Avenue, is a recommended alternative for people traveling by bicycle in the area.

Tentative schedule:

In the next two weeks crews are scheduled to work on water main installation, sidewalk replacement, restoring the street base, paving, installing a joint-utility trench, installing light poles, street light conduits and potholing for upcoming work.

The work listed below is scheduled for daytimes, 7:00 a.m. to 8:00 p.m. Planned night work is italicized. The night shift for construction is 8:00 p.m. to 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit SFMTA.com/VanNess.

Tuesday through Friday, May 28 through May 31

  • Lombard to Greenwich *Due to street base repair work, Greenwich Street from Polk to Van Ness will be closed to regular traffic during work hours on Tuesday, May 28.
  • Greenwich to Filbert *Due to street base repair work, Greenwich Street from Polk to Van Ness will be closed to regular traffic during work hours on Tuesday, May 28.
  • Union to Green
  • Green to Vallejo
  • Vallejo to Broadway
  • Broadway to Pacific
  • Pacific to Jackson
  • Jackson to Washington
  • Washington to Clay Night work is also scheduled Tuesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Clay to Sacramento Night work is also scheduled Tuesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Sacramento to California Night work is also scheduled Tuesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • California to Pine (Tuesday through Friday only) Night work is also scheduled Tuesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Pine to Bush (Tuesday through Friday only) Night work is also scheduled Tuesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Bush to Sutter (Tuesday through Friday only)
  • Geary to O'Farrell Night work is also scheduled Wednesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • O'Farrell to Ellis Night work is also scheduled Wednesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Eddy to Turk Night work is also scheduled Monday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Turk to Golden Gate Night work is also scheduled Monday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Golden Gate to McAllister (Thursday and Friday only)
  • McAllister to Grove
  • Hayes to Fell
  • Market to Mission Night work is scheduled Tuesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. *Disruptive noise is expected.

Monday through Friday, June 3 through June 7

  • Lombard to Greenwich
  • Union to Green
  • Green to Vallejo
  • Vallejo to Broadway
  • Broadway to Pacific
  • Washington to Clay Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Clay to Sacramento Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Sacramento to California Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • California to Pine Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Pine to Bush Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Geary to O'Farrell Night work is scheduled Monday between the hours of 8:00 p.m. and 7:00 a.m.
  • O'Farrell to Ellis Night work is scheduled Monday between the hours of 8:00 p.m. and 7:00 a.m.
  • Ellis to Eddy
  • Eddy to Turk
  • Turk to Golden Gate
  • Golden Gate to McAllister
  • McAllister to Grove Night work is also scheduled Tuesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Grove to Hayes Night work is also scheduled Tuesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Hayes to Fell (Monday through Thursday only) Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. *Disruptive noise is expected.
  • Market to Mission Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. *Disruptive noise is expected.
  • Mission to Howard Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. *Disruptive noise is expected.