Van Ness Avenue Construction Forecast: November 18 - November 30, 2018

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit
Walking

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit SFMTA.com/VanNess.

The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.

Tentative schedule:

In the next two weeks crews are scheduled to work on sewer and water main installation, sidewalk replacement, installing a joint utility trench, street light conduits and potholing for upcoming work.

Sunday, November 18 *Night work is scheduled between the hours of 8:00 p.m. and 7:00 a.m..

  • Sacramento to California
  • California to Pine
  • Ellis to Eddy
  • Eddy to Turk
  • McAllister to Grove
  • Grove to Hayes

Monday through Wednesday, November 19, through November 21

  • Bay to Francisco
  • Filbert to Union
  • Union to Green
  • Green to Vallejo
  • Vallejo to Broadway
  • Broadway to Pacific
  • Pacific to Jackson
  • Washington to Clay *Intensive noise and vibration is expected.
  • Sacramento to California Night work is scheduled Monday and Tuesday, between the hours of 8:00 p.m. and 7:00 a.m.
  • California to Pine Night work is scheduled Monday and Tuesday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Sutter to Post
  • Post to Geary
  • Ellis to Eddy Night work is scheduled Monday and Tuesday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Eddy to Turk Night work is scheduled Monday and Tuesday, between the hours of 8:00 p.m. and 7:00 a.m.
  • McAllister to Grove Night work is scheduled Monday and Tuesday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Grove to Hayes Night work is scheduled Monday and Tuesday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Hayes to Fell *Intensive noise and vibration is expected.
  • Fell to Market *Intensive noise and vibration is expected.
  • Market to Mission Night work is scheduled Monday and Tuesday, between the hours of 8:00 p.m. and 7:00 a.m.

Monday through Friday, November 26 through November 30

  • Lombard to Greenwich
  • Filbert to Union
  • Union to Green
  • Green to Vallejo
  • Vallejo to Broadway
  • Broadway to Pacific
  • Pacific to Jackson
  • Jackson to Washington
  • Washington to Clay (Monday through Wednesday only) *Intensive noise and vibration is expected.
  • California to Pine (Thursday and Friday only) *Intensive noise and vibration is expected.
  • Geary to Post
  • Post to Geary
  • Geary to O'Farrell Night work is also scheduled Friday, November 30 between the hours of 8:00 p.m. and 7:00 a.m.
  • O'Farrell to Ellis Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Ellis to Eddy Night work is also scheduled Monday through Thursday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Eddy to Turk
  • Turk to Golden Gate
  • McAllister to Grove
  • Grove to Hayes
  • Hayes to Fell (Monday and Tuesday only) *Intensive noise and vibration expected.
  • Fell to Market *Intensive noise and vibration expected. Night work is also scheduled Thursday and Friday, between the hours of 8:00 p.m. and 7:00 a.m. Intensive noise and vibration is expected.

*We are working on improving the format of our weekly construction forecasts. Please share your feedback with staff at VanNessBRT@SFMTA.com