Van Ness Avenue Construction Forecast: October 22 - November 2, 2018

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit
Walking

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit SFMTA.com/VanNess.

The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.

Tentative Schedule:

Lombard to Greenwich: Monday through Friday, October 29 through November 2, crews are scheduled to work on sidewalk replacement.

Night work is scheduled Monday through Friday, October 29 through November 2, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Greenwich to Filbert: Monday through Friday, October 29 through November 2, crews are scheduled to work on sidewalk replacement.

Filbert to Union: Monday through Friday, October 22 through October 26, and Monday through Friday, October 29 through November 2, crews are scheduled to work on sidewalk replacement.

Union to Green: Wednesday through Friday, October 24 through October 26, and Monday through Friday, October 29 through November 2, crews are scheduled to work on sidewalk replacement.

Vallejo to Broadway: Monday through Friday, October 22 through October 26, crews are scheduled to work on sidewalk replacement.

Pacific to Jackson: Monday through Saturday, October 22 through October 27, crews are scheduled to work on sidewalk replacement.

Clay to Sacramento: Monday through Friday, October 29 through November 2, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Sacramento to California: Monday through Friday, October 29 through November 2, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

California to Pine: Monday through Friday, October 22 through October 26, and Monday through Friday, October 29 through November 2, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Pine to Bush: Monday through Friday, October 22 through October 26, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Bush to Sutter: Monday through Friday, October 22 through October 26, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Sutter to Post: Monday through Friday, October 22 through October 26, and Monday through Friday, October 29 through November 2, crews are scheduled to work on sewer main installation and sidewalk replacement. Access to Daniel Burnham Court will be limited.

Post to Geary: Night work is scheduled Monday through Friday, October 22 through October 26, and Monday through Friday, October 29 through November 2, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on updating the emergency firefighting system. Disruptive noise is expected.

Geary to O'Farrell: Monday through Friday, October 22 through October 26, crews are scheduled to work on installing a joint-utility trench, to work on water main installation, and to perform street lights work. Crews are also scheduled to pothole for upcoming work. Monday through Friday, October 29 through November 2, crews are scheduled to install a joint-utility trench and to work on sidewalk replacement.

O’Farrell to Ellis: Monday, October 29 through Wednesday, October 31, crews are scheduled to pothole for upcoming work.

Ellis to Eddy: Monday through Friday, October 22 through October 26, and Monday through Friday, October 29 through November 2, crews are scheduled to work on sewer main installation and sidewalk replacement.

McAllister to Grove: Monday through Friday, October 22 through October 26, crews are scheduled to work on sewer main installation.

Grove to Hayes: Monday through Friday, October 22 through October 26, crews are scheduled to work on sewer main installation.

Fell to Market: Monday through Friday, October 29 through November 2, crews are scheduled to work on sewer and water main installation. Intensive noise and vibration is expected.

Night work is scheduled Monday through Friday, October 29 through November 2, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Mission: Night work is scheduled Tuesday through Thursday, October 23 through October 25, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.