West Portal Station Decorative Crosswalk Work Rescheduled to Start Week of September 2, Bikeshare and Planters Added in Horseshoe

Share this:

August 26, 2025

Horseshoe improvements are nearly complete! This month, crews installed planters and a bikeshare station. We have been receiving a lot of positive feedback about how these improvements are improving the look and feel of the station area.


An overhead photo of West Portal Station shows new street murals, a bikeshare station and planters outside the station.


Learn more about how to use bikeshare in San Francisco.


Outside of West Portal Station, a new bikeshare station is filled with bikes.


Rescheduled to Week of September 2: Painting decorative crosswalk during the evening hours

Due to a supplier issue, we have rescheduled the work to paint decorative crosswalks near the station. We now expect this work to begin the week of Tuesday, September 2.

Crews will paint decorative crosswalks at all crosswalks at Ulloa Street and West Portal Avenue. They will also paint a decorative crosswalk on Ulloa Street crossing Lenox Way. This work will take place late at night to minimize disruptions.  

If you live close to the locations of this work, you may have received a notice from the contractor performing this work, Hernandez Engineering. This notice included information about what to expect when this work is completed. It is anticipated to only require two nights of work. As a contingency, the notice says work could take place over six nights.  

What to expect

  • We expect this work to last two weekday nights. We expect work to take place between 7 p.m. and 7 a.m. Work next to the tracks will occur between 1 a.m. and 5 a.m. when rail service is not operating.  

Muni service impacts:  

  • We do not expect any impact to Muni service. Work next to the tracks will occur when rail service is not operating.
  • Crosswalk locations may change while work is being performed at Ulloa Street and West Portal Avenue. Follow posted signage.

Traffic Impacts:

  • Crews will work on one side of a crosswalk at a time. The intersection will never be fully closed.  
  • There may be times when northbound drivers on West Portal Avenue (toward Ulloa Street) or eastbound or westbound drivers on Ulloa Street (toward West Portal Avenue) will need to use alternate routes.  
  • Follow any posted temporary detours. Be mindful of workers in the intersection. 

Parking impacts:  

  • Crews will temporarily reserve several parking spaces at two locations. These locations are Lenox Way as well at Ulloa Street between West Portal Avenue and Claremont Boulevard. Watch for signs. 

Noise impacts:  

  • There may be some noise during this work.

These changes are being implemented as part of the West Portal Station Safety and Community Space Improvements Project. These improvements are the last items to be installed as part of the project. Later this year, we expect to share a draft evaluation on all project changes. The goal of this evaluation will be assessing how closely we are meeting the project's goals.