Van Ness Avenue Construction Forecast: September 10 - September 21, 2018

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit SFMTA.com/VanNess.

The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.

Tentative Schedule:

Lombard to Greenwich: Monday through Friday, September 10 through September 14, and Monday through Friday, September 17 through September 21, crews are scheduled to work on sewer main installation.

Night work is scheduled Monday through Wednesday, September 17 through September 19, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation. Disruptive noise is expected.

Filbert: Night work is scheduled Thursday, September 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.

Union: Wednesday through Friday, September 12 through September 14, and Monday through Friday, September 17 through September 21, crews are scheduled to work on water main installation.

Green to Vallejo: Monday through Friday, September 10 through September 14, crews are scheduled to work on sidewalk replacement.

Night work is scheduled Wednesday, September 12, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.

Pacific: Night work is scheduled Monday, September 10 and Tuesday, September 11, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.

Jackson to Washington: Monday through Friday, September 10 through September 14, and Monday through Friday, September 17 through September 21, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Washington to Clay: Monday through Friday, September 10 through September 14, crews are scheduled to pothole for upcoming water work.

Clay to Sacramento: Monday through Friday, September 10 through September 14, crews are scheduled to pothole for upcoming water work.

Sacramento to California: Monday through Friday, September 10 through September 14, crews are scheduled to work on sewer main installation and to pothole for upcoming water work. Intensive noise and vibration is expected.

Night work is scheduled Monday through Thursday, September 10 through September 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on updating the emergency firefighting water system. Disruptive noise is expected.

California to Pine: Monday through Friday, September 10 through September 14, crews are scheduled to work on sewer main installation and to pothole for upcoming water work. Intensive noise and vibration is expected.

Night work is scheduled Monday through Thursday, September 10 through September 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on updating the emergency firefighting water system. Disruptive noise is expected.

Pine to Bush: Monday through Friday, September 10 through September 14, crews are scheduled to pothole for upcoming water work. Monday through Friday, September 17 through September 21, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Night work is scheduled Monday through Wednesday, September 10 through September 12, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on updating the emergency firefighting water system. Disruptive noise is expected.

Bush to Sutter: Monday through Friday, September 10 through September 14, and Monday through Friday, September 17 through September 21, crews are scheduled to work on sewer main installation and on installing a joint-utility trench. Intensive noise and vibration is expected.

Night work is scheduled Monday through Wednesday, September 10 through September 12, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on updating the emergency firefighting water system. Disruptive noise is expected.

Sutter to Post: Monday through Friday, September 10 through September 14, and Monday through Friday, September 17 through September 21, crews are scheduled to install sewer main and a joint-utility trench. Intensive noise and vibration is expected. Monday through Wednesday, September 10 through September 12, crews are also scheduled to work on water main installation. Monday through Friday, September 17, through September 21, crews are also scheduled to work on sidewalk replacement.

Post to Geary: Wednesday, September 19, and Thursday, September 20, crews are scheduled to work on water main installation.

Night work is scheduled Wednesday, September 19, through Friday, September 21, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on updating the emergency firefighting system. Disruptive noise is expected.

Geary to O'Farrell: Monday, September 10, crews are scheduled to work on water main installation and to pothole for upcoming work. Monday through Thursday, September 17, through September 20, crews are scheduled to work on water main installation.

Night work is scheduled Thursday through Friday, September 13 through September 14, and Monday through Friday, September 17 through September 21, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on updating the emergency firefighting system. Disruptive noise is expected and access to Myrtle street from the west side of Van Ness Avenue might be limited.

O'Farrell to Ellis: Monday through Friday, September 10 through September 14, and Monday through Friday, September 17 through September 21, crews are scheduled to work on sidewalk replacement. rews are also scheduled to work on water main installation.

Ellis to Eddy: Monday through Friday, September 10 through September 14, crews are scheduled to work on sidewalk replacement. Tuesday, September 11, crews are also scheduled to work on water main installation. Monday through Wednesday, September 17 through September 19, crews are scheduled to work on sewer main installation.

Night work is scheduled Monday, September 17, and Tuesday, September 18, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on water main installation.

Eddy to Turk: Monday, September 10 and Tuesday, September 11, crews are scheduled to work on water main installation. Monday through Friday, September 17 through September 21, crews are scheduled to work on sewer main installation and sidewalk replacement.

Night work is scheduled Monday, September 17, and Tuesday, September 18, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on water main installation.

Golden Gate to McAllister: Monday through Friday, September 17 through September 21, crews are scheduled to work on sidewalk replacement.

McAllister to Grove: Monday through Friday, September 10 through September 14, and Monday through Friday, September 17 through September 21, crews are scheduled to work on sewer main installation and to install a joint-utility trench. Intensive noise and vibration is expected.

Grove to Hayes: Monday through Friday, September 10 through September 14, and Monday through Friday, September 17 through September 21, crews are scheduled to work on sewer main installation and on installing a joint-utility trench. Intensive noise and vibration is expected. Wednesday through Friday, September 19 through September 21, crews are also scheduled to pothole for upcoming work.

Hayes to Fell: Monday through Friday, September 10 through September 14, crews are scheduled to work on sewer main installation and to pothole for upcoming work. Intensive noise and vibration is expected. Monday, September 17, and Tuesday, September 18, crews are scheduled to pothole for upcoming work.

Fell to Market: Monday through Friday, September 10 through September 14, and Monday through Friday, September 17 through September 21, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Night work is scheduled Monday through Friday, September 17 through September 21, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Mission: Night work is scheduled Wednesday through Friday, September 12 through September 14, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to perform sewer work. Disruptive work is expected.