ATTN: There are only two coaches in service on the 36 right now. The third coach needed to pull back into the bus yard. Expect longer IB/OB wait times for about the next hour until we can get another coach in svc. (More: 14 in last 48 hours)

This page has older content

Please see Related Projects on this page for current project information. We are keeping this page as a record of SFMTA outreach.

Central Subway Construction Update 9/27/13

Construction Update

September 28-October 7, 2013

During the next 10 days, tunneling and tunneling preparatory work will continue in southern SoMa, Union Square and North Beach. Work to prepare for station construction is continuing in Chinatown and northern SoMa. 

For descriptions of construction impacts in each neighborhood, scroll down or click on the links below. We also post construction, traffic detour and Muni impact information on our project Google Map.

Construction impacts are planned to change at these locations by October 7:

 

  • Southern SoMa (Harrison to King/Berry): During the week of September 30, one lane of the I-80 off-ramp at 4th and Bryant may close. 4th Street between Harrison and Bryant may fully close some evenings and weekends to allow for the installation of tunnel boring machine segments. Two lanes of traffic will remain open at all other times. Contact us at central.subway@sfmta.com if you have questions about the closure schedule. On Bryant Street at 5th Street, the left lane and several parking spaces will remain closed.
     
  • Northern SoMa (Market to Harrison):  On 4th Street between Folsom and Harrison, the parking lane and one lane of traffic on the east side of the street will close Saturday, September 28 to allow for ground improvement work. 4th Street between Howard and Folsom will remain open to traffic, with demolition of the 76 gas station commencing next week. On 4th Street between Market and Stevenson, at least three lanes of traffic will be open.
     
  • Chinatown: Station contractor Tutor Perini will install monitoring devices and cap utilities at the Chinatown Station site (933-949 Stockton Street). Several parking spaces may be closed on the east side of Stockton Street and on both sides of Washington Street adjacent to the building. The sidewalk adjacent to the building will be closed to pedestrians for approximately two weeks. A partial lane closure may be in effect on Washington Street just west of Stockton Street. Night work will be underway from October 2-4, with traffic impacted at the intersection of Stockton and Washington on these nights. 

 

  • North Beach: Construction of a retrieval shaft, to be used to remove two tunnel boring machines, is commencing at the Pagoda Palace site. The first activity is to install a sound wall that will buffer construction noise. Construction hours are Monday to Saturday, 7 a.m. to 7 p.m. All local roadways will remain open. Parking and walkways may be impacted in front of the Pagoda Palace property while equipment mobilization is in progress.

At these locations, current construction impacts are planned to continue until
October 7:

  • Union Square: Stockton Street between Geary and Ellis will remain closed to vehicle traffic. Ellis Street between Stockton and Powell will remain closed to westbound traffic.

We appreciate your patience and support while we build this essential upgrade to San Francisco's public transportation system.

-The Central Subway Team
At the tunnel launch site, crews install a conveyer system to transport tunnel spoils from the tunnels. Southern SoMa

4th Street from Harrison to King/Berry

On 4th Street between Harrison and Bryant streets, the contractor has constructed a major excavation known as a launch box at the site where the Central Subway tunnel begins. After assembly of a tunnel boring machine (TBM) underground, tunneling started this summer. Assembly of a second TBM is now in progress.

Planned construction:

 

  • Construct tunnel for southbound trains (TBM Mom Chung)
  • Assemble TBM Big Alma
  • Test and commission TBM Big Alma

Traffic and pedestrian impacts:

 

 

  • The two lanes on the east side of the street (left lanes for southbound traffic) will remain open to vehicle traffic except as described below.
  • One lane of the I-80 off-ramp at 4th and Bryant may be closed the week of Sept. 30
  • The block may close to traffic from 8 p.m. to 5:30 a.m. on weeknights and all day Saturday and Sunday. When the Giants have home games, the closure will start an hour after the game ends.
  • The sidewalk on the west side of the block will remain closed; the sidewalk on the east side of the block will remain open.
  • On Bryant Street at 5th Street, the left lane and several parking spaces will be closed.

Traffic and pedestrian controls are in place. For more information on construction impacts at this site, check out this blog post.
4th Street from above
The roadway on 4th Street between Howard and Folsom is now reopened to traffic.
Northern SoMa

 

4th Street from Market to Harrison

On 4th Street between Howard and Folsom streets, the contractor has constructed below-ground walls, called headwalls, at the site of the future Yerba Buena/Moscone Station. Preparatory work for station construction is now in progress within the site of the old 76 gas station.

The contractor completed ground improvement work (installation of compensation grout tubes) on 4th Street between Market and Stevenson. Work will resume when the tunnel boring machines pass through this area.

On 4th Street between Folsom and Harrison, the contractor will perform ground improvements while the tunnel boring machines pass beneath the roadway. 

Planned construction (Market to Stevenson):

  • Restore traffic lanes and parking lane
  • Construction will resume when the tunnel boring machines pass beneath this area

Traffic and pedestrian impacts (Market to Stevenson):

  • Three lanes will be open to traffic until restoration is complete

Planned construction (Howard to Folsom):

  • Abate hazardous materials at 260-266 4th Street (former 76 gas station site)
  • Begin demolishing 76 gas station

Traffic and pedestrian impacts (Howard to Folsom):

  • None planned

Planned construction (Folsom to Harrison):

  • Test ground conditions and improve ground
  • Construction is planned to start Saturday, Sept. 28

Traffic and pedestrian impacts (Folsom to Harrison):

 

  • The parking lane and one lane of traffic on the eastern side of the street (in front of Whole Foods) will be closed

Construction on Stockton Street
Work continues on Stockton Street, the site of the future Union Square/Market Street Station. Union Square

 

Stockton Street from Market to Post

On Stockton Street between Geary and Ellis streets, the contractor is installing below-ground walls called headwalls at the site of the future Union Square/Market Street Station. In addition, ground improvement is underway on Ellis Street between Stockton and Powell streets.

Planned construction:

 

  • Stockton between Ellis and O'Farrell: Perform permeability tests of underground walls; commence restoration of the site
  • Stockton between O'Farrell and Geary: Install headwalls
  • Ellis between Stockton and Powell: Perform ground improvements from inside the Ellis Street shaft
  • On Stockton Street, the contractor will continue working two shifts on weekdays, from 6 a.m. to 12:30 a.m. On Saturdays, work hours will be 6 a.m. to 12:30 a.m.
  • On Ellis Street, the contractor will work 24 hours a day on weekdays

Traffic, transit and pedestrian impacts: 

 

  • Stockton Street between Geary and Ellis is closed to all vehicles except emergency vehicles
  • Ellis Street between Stockton and the Ellis-O'Farrell Garage (between Stockton and Powell) is closed to westbound traffic
  • The 38/38L Geary may experience delays around Union Square
  • Sidewalks on Stockton Street between Ellis and Geary will remain open, but they may be narrowed to facilitate construction

More information about construction at this site is available in this construction notice and this press release. Photo of Chinatown Station property
At a recent community meeting, Central Subway team members answer questions about Chinatown Station construction. Chinatown

Stockton Street from Sacramento to Broadway

To prepare to build the Chinatown Station, contractor Tutor Perini will demolish the existing building at 933-949 Stockton Street. Preparatory construction is now underway.

Planned construction:

  • Remove hazardous materials
  • Install instruments
  • Cap utility lines (some work in street)

Traffic, transit and pedestrian impacts:

  • Several parking spaces may be closed on the west side of Stockton Street and both sides of Washington Street in front of the building
  • The sidewalks in front of the building on Stockton and Washington streets will be closed for approximately two weeks
  • A partial lane closure may be in effect on Washington Street just west of Stockton Street
  • From October 2 to 4, traffic may be impacted at the intersection of Stockton and Washington streets. Traffic controls will be in place to facilitate the flow of traffic.

Photo of inside of Pagoda theater
With Pagoda Palace demolition complete, work is commencing on a retrieval shaft to remove the tunnel boring machines from the ground. North Beach

Powell Street from Union to Columbus

On private property at 1731-1741 Powell Street, the contractor is preparing to construct a walled excavation known as a retrieval shaft at the site where tunneling will end. The two tunnel boring machines will be removed from the ground at this location.

Demolition of the Pagoda Palace is now complete. The second phase of construction is to construct the retrieval shaft.

Planned construction:

 

  • Install monitoring instruments
  • Construct sound wall to mitigate construction noise
  • Construction hours for the retrieval shaft are Monday to Saturday, 7 a.m. to 7 p.m.

Traffic, transit and pedestrian impacts:

 

  • Several parking spaces may be closed in front of the property during construction hours.
  • The sidewalk in front of the property may be closed. A temporary walkway will be in place around the construction zone when the sidewalk is closed.

Central Subway Construction Fast Facts

Project Alignment: 4th Street between Berry and Market streets; Stockton Street between Market Street and Columbus Avenue; Powell Street between Union Street and Columbus Avenue; Columbus Avenue between Powell and Filbert streets.

Transit Reroutes: The southbound 8X/8AX/8BX Bayshore Express, 30 Stockton, 45 Union/Stockton and 91 Owl Muni bus routes have been rerouted to accommodate construction in Union Square and SoMa. These reroutes will remain in effect throughout the duration of Central Subway construction. More information is available online here.

Contact Us: Should you have questions about construction or the Central Subway Project, don't hesitate to contact our team. You can reach us at central.subway@sfmta.com or by phone at 415-701-4371.

For More Information: The Central Subway team posts frequent project updates on a variety of social media outlets. To find out more about the project and construction progress, follow us on Facebook, Twitter, Instagram or Flickr, and check out our blog.

Construction schedules are subject to change.