Geary Rapid Project Construction Forecast: September 11 - September 24, 2021

Service Affected
Accessibility
Taxi
Driving
Transit
Walking

Photo: New crosswalks at the intersection of Geary Boulevard and Steiner Street.

Photo: New crosswalks at the intersection of Geary Boulevard and Steiner Street.  

Utility work on the Geary Rapid Project, in coordination with San Francisco Public Utilities Commission, is officially complete! Crews connected properties’ water service to the new water main at the last remaining location at Geary and Kearny last month. In total, 1.5 miles of new sewer and almost 3 miles of upgraded water mains were installed along Geary, replacing the previous 100-year-old infrastructure. 

Surface improvements managed by San Francisco Public Works are still underway, including utility trench restoration and repaving. Red transit lane treatments are also being installed. 

The following two-week construction forecast is subject to change due to weather delays or unexpected field conditions.  

Masonic Avenue – Van Ness Avenue  

Mondays through Fridays between 8 a.m. and 7 p.m.: 

  • Median work is planned for the week of September 13 on Geary Boulevard at Buchanan Street
  • Installation of red thermoplastic colorization in the existing transit-only lanes is planned for the weeks of September 13 and September 20 on Geary Boulevard between Webster and Van Ness streets
  • Minor punch list repairs within the sidewalk and roadway are planned for the weeks of September 13 and September 20 on Geary Boulevard between Masonic and Webster streets

Van Ness Avenue – Market Street  

Mondays through Fridays between 7 a.m. and 4 p.m.: 

  • Roadway and sidewalk work are planned for the weeks of September 13 and September 20 on Geary Street between Stockton and Grant streets and at the intersections of Geary at Mason and at Kearny streets

Some parking will be temporarily restricted in construction zones and traffic lanes will be modified during active work. There may be brief vibrations during sidewalk and roadway excavation.  

Questions or concerns? Contact us atGearyRapid@SFMTA.comor 415.646.2300. 


Vandalism Relief Grant Program 

The Office of Economic and Workforce Development (OEWD) is launching a new vandalism relief grant program later this summer. Businesses can apply for $1,000 or $2,000 grants to go towards storefront vandalism-related damages. Incidents are retroactive to January 1, 2021. Learn more and sign up to receive updates about the program at OEWD.org/VandalismRelief


For the most up-to-date Muni service information, parking enforcement and other updates, visit the SFMTA COVID-19  page. 


Sign up for Geary Rapid Project updates via email or text