L Taraval Improvement Project Segment B Update and Forecast - January 16 - 28, 2023

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit
Walking
Route(s) Affected

L Taraval Improvement Project Segment B Update and Forecast - January 16 - 28, 2023   

The onset of the new year came with extreme weather conditions, delaying construction activities on the L Taraval Improvement Project. Construction crews monitored areas that were prone to flooding and took preventative measures to ensure the roads stayed clear. In the coming weeks, work continues on water and sewer lines, as well as on the overhead contact system (OCS) that powers the trains. OCS work is now focused on foundation work to prepare for the installation of new poles. Construction teams will be excavating and jackhammering pavement, which may cause vibrations. Materials are also being temporarily staged nearby. Dust control and housekeeping measures are in place at active construction and staging locations.

The inbound stop at Taraval and 15th has been relocated across the intersection until fall 2024.

General construction hours are Monday to Friday between 8:00 a.m. and 4:00 p.m. Construction schedules are subject to change. “No Parking” signs will be posted in construction and staging areas, and intersections may be closed to through traffic on Taraval Street.

Multiple agencies are performing infrastructure work in the area. This includes work by Public Works on 19th Avenue, Public Utilities Commission at Vicente and Wawona streets and PG&E along Taraval Street.

L Taraval Improvement Project – Segment B

Construction work is scheduled to be performed - January 16 - 28, 2023

Taraval Street

15th Avenue and Taraval Street: waterline work

16th to 17th avenues: waterline work, excavate, measure and connection holes

16th to 18th avenues: OCS Pole work

23rd to 24th avenues: sewer line work

24th to 26th avenues: OCS Pole work

26th to 29th avenues: waterline work

28th to 30th avenues: OCS Pole work

Sunset Boulevard to 34th Avenue: water line work, excavate and shore, connection holes

Ulloa Street

14th Avenue to Funston Street: water line work, excavation and shoring, service change over

Temporary staging locations

14th Avenue west side from Ulloa to Vicente streets

16th Avenue west side from Taraval to Ulloa streets

24th Avenue east side from Taraval to Santiago streets

25th Avenue east side from Taraval to Ulloa streets

28th Avenue east side from Taraval to Ulloa streets

29th Avenue west side from Taraval to Santiago streets